The Law Commission had recommended amending the definition of
Party
under Section 2 (1) (h) of the Arbitration and Conciliation Act, 1996 to include
person claiming through or under such party. However, this recommendation
was not accepted.
However, by 2015 amendment, Section 8 of the Arbitration and Conciliation Act
(Act) was amended, which reads as follows:
Section 8 (1):
A judicial authority, before which an action is brought in a
matter which is the subject of an arbitration agreement shall, if a party to the
arbitration agreement or any person claiming through or under him, so applies
not later than the date of submitting his first statement on the substance of
the dispute, then, notwithstanding any judgment, decree or order of the Supreme
Court or any Court, refer the parties to arbitration unless it finds that prima
facie no valid arbitration agreement exists.
The 2015 amendment to Section 8 of the Act gives enough leeway to include third
party claims in the overall claims of the petitioner (party to the Arbitration
Agreement) and makes it clear that persons claiming through or under the party
to arbitration agreement can claim the benefit of such agreement.
In
Chloro Controls(I) P.Ltd vs Severn Trent Water Purification[1], the Supreme
Court held that though the scope of an arbitration agreement is limited to the
parties who entered into it and those claiming under or through them.....
In
Ameet Lalchand Shah vs Rishabh Enterprises[2], the Supreme Court revisited
the principles expounded in Chloro Controls India Private Limited Vs. Severn
Trent Water Purification Inc.
and Others and held that:
- Principally four amendments to Section 8(1) of the Act have been
introduced by the 2015 Amendments - one being that the relevant "party" that
is entitled to apply seeking reference to arbitration has been
clarified/amplified to include persons claiming "through or under" such a
party to the arbitration agreement;
- The Parties to the agreements namely Rishabh and Juwi India:
- Equipment and Material Supply Agreement; and
- Engineering, Installation and Commissioning Contract and the parties to
Sale and Purchase Agreement between Rishabh and Astonfield are one and the same as that of the parties in the main
agreement namely Equipment Lease Agreement. All the four agreements are inter-connected. This is a case where several parties are involved in a
single commercial project executed through several agreements/contracts. In such
a case, all the parties can be covered by the arbitration clause in the
main agreement.
Thus, from a conjoint reading of Section 8 and the above judgements, it can be
inferred that a party to an arbitration can claim amounts
for and on behalf
of a third party, who may or may not be an affiliate or a group company.
Also, the intention of legislature in not accepting the Law Commission
recommendation of including
person claiming through or under such party in
the
Party definition under Section 2(1)(h) of the Act could be that the
legislature did not intend to give the third parties an opportunity to arbitrate
their individual claims separately. That would have resulted into multiple
claims arising out of the same transaction relating to a project/principal
agreement being filed and thereby increasing the judicial burden.
Therefore, a party to a dispute before an Arbitrator can claim money for and on
behalf of a third party on the ground that the third party worked on the project
Doctrine of Privity of Contract
In accordance with the common law principle of doctrine of privity of contract,
a contract cannot confer rights or impose obligations upon any person who is not
a party to the contract. As such, the third parties to an Arbitration Agreement,
who have worked on the transaction forming part of the Arbitration Agreement for
and on behalf of a party to the Arbitration Agreement, cannot directly claim but
have to claim through a party to the Arbitration Agreement.
End-Notes:
- Chloro Controls(I) P.Ltd vs Severn Trent Water Purification, Supreme
Court [Civil Appeal No. 7134 of 2012 (Arising out of SLP (C) No. 8950 of
2010)]; Judgement dated 28th September 2012.
- Ameet Lalchand Shah v Rishabh Enterprises, Supreme Court [Civil Appeal
No. 4690 of 2018 (Arising out of SLP (C) No. 16789 of 2017)]; Judgement
dated 03rd May 2018.
Please Drop Your Comments