This case is related to the sale of land and the question before the court
was certain supervening events which affected the material part of it and would
those events lead to its discharge. The doctrine of frustration of contracts
when an act becomes impossible to perform or unlawful comes under the purview of
Section 56 of the Indian Contract Act, 1872. By
Satyabrata v Mugneeram,
[1] the Supreme Court established the scope of Section 56 of ICA [2] that
impossibility, as mentioned in the said Section, is used in a practical and not
in the literal sense [3]. It also held that it is not permissible to import
English law to the statutory provisions of ICA.
Facts:
The Respondent's company owned a large tract of land in Calcutta. It started a
scheme for the development of the land for residential purposes and divided the
land into different plots. The company entered into agreements with purchasers
for the sale of the different plots and accepted a small amount of earnest money
at the time of sale of land. The company undertook the job of constructing roads
and drains, necessary for residential purposes. The plots would be given after
the construction and payment of balance amount by the buyers.
Bejoy Krishna Roy entered into the agreement with the company and paid the
earnest money deposit of Rs. 101 on 5th August 1941. On 30th November 1941, the
appellant was made the nominee of the above land. It so happened that
subsequently the land was requisitioned by the Collector, 24 - Paragnas under
Defence of India rules for military purposes. As a consequence, in November
1943, the company decided to treat the agreement cancelled but gave the
appellant the option of either taking the earnest money back or paying the
balance money and the company would continue its work after the termination of
the war.
The appellant refused both the options. He filed a suit on 18th January 1946 and
claimed that the company was bound to the terms of the agreement.
Issues:
- Did the plaintiff have a locus standi for instituting the suit?
- Did the contract become frustrated under Section 56 of ICA?
- Does English law of frustration apply in India?
Judicial History:
The trial court passed its judgement in the favour of the Appellant (then the
plaintiff). The respondents filed for an appeal in the District Court which was
dismissed. A second appeal was filed in the High Court which gave its judgment
in the favour of the respondent. The appellant, therefore, filed for an appeal
in the Supreme Court of India under Article 133 [4] of the Indian Constitution.
Judgment:
The Supreme Court stated that English principles of Frustration of Contract on
basis of which the judgement of the High Court was passed is not applicable in
the statutory provisions of the Indian Contract Act. It also said that the
performance of the contract has not become impossible. The Court pointed out,
the company had not commenced its work when the land was requisitioned,
therefore, there was no interruption of work. Secondly, there was no time limit
implied in the contract for the completion of construction of the roads and
drains.
It was laid by the trial court as well as the lower appellate court that the
appellant was a real assignee of Bejoy Krishna Roy on the issue of the latter's
rights on filing the suit.
Appeal allowed.
Principles:
- English laws only have a persuasive value in India.
- A contract becomes frustrated when the very foundation gets disturbed.
- Section 56 of ICA [2] takes the word impossibility' in a practical sense
and not a literal sense.
Critical Analysis:
The doctrine of frustration was first dealt in modern times in Taylor v.
Caldwell. A music hall was burnt down in which concerts were supposed to be
performed by the plaintiff on certain specific days. The court held that the
defendant (the music hall co.) was excused as its performance became impossible.
Over time, English law has pronounced many theories and principles relating to
the law of frustration. However, it was made clear by this case that in India we
have statutory provisions to be followed under Section 56 of the Indian Contract
Act.
It has 3 provisions. First says an agreement to do an act impossible in itself
is void.
Second says contracts to do any act which afterwards becomes impossible or
unlawful are void. So, when do contracts become impossible? First, impossibility
does not apply to the cases where the contract contains an implied term which
discharges them from the performance of the contract.
In
Smt. Sushila Devi v. Hari Singh, the Supreme Court said, Section 56
lays down a positive law and doesn't leave the matter determined according to
the intention of parties.
Section 56 [2] is dealt with when the matter is not determined to the intention
of parties. It is applied when parties did not have an intention regarding the
supervening event and when there is no implied term in the contract. Another
important aspect to check for the application of impossibility is that the
foundation of the contract gets upset.
In this case of
Satyabrat Ghose v. Mugneeram Bangur, though the land gets
requisitioned by the government, impossibility does not apply because:
They did not start their work when the land got requisitioned. Therefore, there
was no interruption in the work.
As the defendant pleads there would be an indefinite delay in performance of the
contract so the impossibility should be applied. But there was no time limit
described in the contract and the requisition was only temporary. So, there was
no indefinite delay.
The third provision of Section 56 [2] says when a person while signing the
contract has reasonable diligence which the other party didn't know must
compensate for the loss faced by the other party.
It can be concluded stating that though theories of law of frustration of
England are not applicable in India, the matter is always determined to the
court which analyzes the contract as presented by the parties and considers the
circumstances around the contract.
Please Drop Your Comments