The Indian Contract Act, 1872 proclaims under section 37 that:
The parties to a
contract must either perform, or offer to perform, their respective promises,
unless such performance is dispensed with or excused under the provisions of
this Act, or of any other law.
The Covid-19 pandemic has indisputably been an
extended period of loss. This loss has manifested in as much a humanitarian form
as that of a commercial and economic one.
The restriction of movement along with
loss of lives is the predominant factor impeding the fulfilment of commercial
contracts in the pandemic 'era'. It is not only detrimental to the financial and
moral health of the breaching party, but also equally threatening to the party
at the other end of the contract.
Nevertheless, given the enterprising nature of legal professionals and scholars,
a much-needed solace is found in the principles of Force Majeure and Frustration
of contracts in the Indian Contract Act,1872.
In light of Force Majeure or the frustration of contracts, unlike singular and
transient events, COVID-19 is ongoing and unprecedented when it comes to
situations the legal field has taken cognizance of in the past. So to say, a
tsunami or an earthquake is an event that occurs once in most scenarios in the
sense of disrupting legally obligating activities. However, the pandemic manages
to continuously call for government authorized restrictions and general
precautions which may prevent transportation and work in full capacity,
consequentially breaching duties of a contract.
Given the implications of Covid-19 on pre-existing contracts, it would not be
far-fetched to assume that potential parties to a contract have begun
incorporating multiple provisions to insulate the dealings of the contracts from
the collateral effects of the pandemic.
For the sake of the following article, I would focus on an analysis of the
commercial implications of COVID- 19 in terms of construing contracts and their
non-fulfilment.
What Is Force Majeure?
A company or corporation may insert a Force Majeure clause in case it intends to
get rid of liability arising if it cannot potentially fulfil a responsibility
stipulated by a given contract or if performing such stipulated duties would
lead to a sizeable loss in reality- on account of reasons beyond its own
control.
The concept of Force Majeure in India has not explicitly been dealt with on a
statutory level. Nevertheless, the following definition noted by Pollock and
Mulla would be fruitful to explore- "A party is excused of non-performance, if
it proves that non-performance was due to an impediment beyond its control, and
it could not have reasonably been foreseen by it at the time of making of the
contract, nor could it have avoided or overcome it or its consequences"[1]
Force majeure, in terms of its literal roots, holds parity with the Latin term
Vis Major, which in turn translates to 'superior force'. Nevertheless, these
terms hold no congruence when it comes to their conventional usage in the legal
context. It has been noted in
Dhanrajmal Gobindram V. Shamji Kalidas & Co.,
that:
"The expression force majeure is not a mere French version of the Latin
expression vis major. It is undoubtedly a term of wider import. Difficulties
have arisen in the past as to what could legitimately be included in force
majeure. Judges have agreed that strikes, breakdown of machinery, which, though
normally not included in vis major are included in force majeure."[2]
The intent of the force majeure provision in the field of Indian Contract Law
can essentially be construed "to save the performing party from the consequences
of anything over which he has no control"[3]
Force majeure has a wider scope than Vis major, wherein Force Majeure includes
events that are both, human-influenced and natural. Vis major solely includes
unanticipated events which have natural roots. So to say, Force Majeure would
include the event of war, but Vis Major would not.
Legal Basis Of The Provision
The concept of Force Majeure has not been explicitly mentioned under any Indian
statute. Nevertheless, Indian legislators have dealt with the topic to an
extent, under section 32 and Section 56 of the Indian Contract Act, 1872.
In multiple decisions, most notably Energy Watchdog v. CERC[4], the apex court
has stated that section 32 of the Contract act would be relevant in case the
Force Majeure event is affiliated with a clause in the contract. On the other
hand, in case the Force Majeure event is not concerned with a clause in the said
contract, section 56 of the Contract Act would be applicable.
Section 32 deals with contingent contracts or contracts which are substantially
based on the occurrence of a given event. Such contracts cannot be enforced by
the law till the time this event of significance has occurred. Moreover, the
contract becomes void if the event in regard has become impossible to perform.
On the other hand, section 56 of the Contract Act deals with the failure of
performance in a two-fold manner. Firstly, it conceives a situation where the
performance of a contract has become impossible consequently. Secondly, and more
primarily, it renders all agreements to perform impossible acts, void.
Characteristics Of A Force Majeure Clause-
Foremost, the unforeseeable event which has occurred must not have been under
the ambit of either parties' assumption as a possibility in the future upon
signing the contract. Secondly, this event of significance must have made the
performance of the parties' contractual duties impossible, or sufficiently
impractical for the party to not make sense for it to perform the same. It is
also conducive in this regard to identify whether a given party has taken any
steps to perform the said obligations in the contract at all.
The postulate regarding sufficient impracticality was propagated in
Satyabrata
Ghose v. Mugneeram Bangur & Co.[5]
Express And Implied Terms In A Given Force Majeure Clause
Typically a Force Majeure clause is exhaustive in nature in the sense that it
provides the list of events that would constitute a force majeure event. As a
natural consequence, the author believes that it would be of outstanding
significance to further define and discuss terms such as 'pandemic' in the legal
field, as subsequent contracts would be witnessing more of such events.
Moreover, it is also given that a majority of the contracting population did not
mention 'pandemic' or related terms specifically on account of the unprecedented
nature of this public health catastrophe.
Therefore, it would be a prerogative of a contracting party to definitively
establish whether the events in a given Force Majeure agreement are entirely
exhaustive or simply descriptive in nature.[6]
On the other hand, concerning implied or rather open-ended terms, the inclusion
of words such as 'unforeseen' and 'beyond reasonable control of the parties' may
be construed to include Covid- 19 as a Force Majeure event under a given Force
majeure clause by a sympathetic court of law.[7]
To supplement the same, not only has the finance ministry referred to Covid- 19
as a 'natural calamity', but the government has also declared the pandemic
situation a disaster under the Disaster Management Act, 2005.[8] Nevertheless,
further clarification is given, where the "invocation of FMC does not absolve
all non- performances of a party to the contract, but only in respect of such
non-performance as is attributable to a lockdown situation or restrictions
imposed under any act or executive order of the government on account of the
COVID-19 global pandemic. It may be noted that, subject to the above- stated,
all contractual obligations shall revive upon the completion of the period."[9]
The condition that the contractual obligations shall be revived upon the
completion of the period of inconvenience serves as an ideal segue into the
distinction between the frustration of a contract and Force Majeure.
Discerning Force Majeure From Frustration Of A Contract
As has been noted in the preceding text, Force Majeure implies the occurrence of
an external event, free from the influence of the party seeking relief from the
contract. Nevertheless, it must be noted that Force Majeure essentially implies
a temporary suspension of contracts instead of permanent cessation of
performance or permanent relief from performance. So to say, once the external
event has ceased to exist, the performance of the duties of the party seeking
relief, must be fulfilled. In the case that this performance is still not
resumed, the party must turn to the termination of the contract. It can
essentially be termed as a contractual remedy, the terms of which are decided
before the execution of the contract by the contracting parties.[10]
Nevertheless, in cases where the occurrence of a supervening event has disabled
the party seeking relief, from performing the obligations of the contract
altogether, it can be referred to as the frustration of a contract. Section 56
of the Indian Contract Act, 1872 deals with the frustration of contracts. The
crux of the provision of frustration of contracts is the 'impossibility' of
performance. It is vital that this section be interpreted prudently and
pragmatically, not giving too much lenience. It is mainly because a given
situation can appear to be seemingly impossible when it might not be absolutely
so. In a condensed manner, the frustration of contracts can be regarded as the
happening of an act that is outside the control of the contract and such an act
makes the performance of the said contract impossible.
Additionally, the supervening event in the case of frustration of contract
should also not have been present before the contract was instituted or while
the parties were in contemplation of the said contract. The event must be
adequate to disturb the commercial essence of the contract. Given the temporary
nature of potential lockdowns under the ambit of Covid-19, the parties seeking
relief by the way of frustration of the contract must prove that the nature of
their given obligation was time-sensitive.
Force Majeure With Reference To Covid-19
It is possible that a given contract explicitly sets out the conditions which
would necessarily precede the invocation of the Force majeure clause. For
instance, the contracting parties can decide if such an invocation would require
a full hindrance of contractual obligations or a partial one would be adequate.
The latter half of such an invocation rests upon the understanding and
discretion of the court which rules such a contest of the clause. The court
would take into account as to how COVID- 19 was specifically responsible in the
non-fulfilment of, or hindrance of the performance of the contract.
Typically, a court would take into account the presence of or lack of a direct
causal link between the non- performance of the contractual obligations and the
force Majeure event the party seeks relief under. The court will also look after
the clause's place with other covenants of the contract and ensure harmonious
construction. Finally, the court would look into the conditions set forth by the
respective Force Majeure clause and test the same against the given facts of the
case.
Moreover, as has been mentioned before, a mere difficulty in performing the
contract would not result in a justification to invoke the force majeure clause
of a given contract. It has to be disruptive enough to affect the essence of
contractual obligations or become counter-productive to the commercial essence
if performed under the given circumstances. Moreover, it was held in the Energy
watchdog case that an increase in the cost of performance of the contractual
obligations would not amount to impossibility or cause enough to invoke a force
majeure event.[11] Therefore, even though the cost of conducting business may
have increased on account of Covid-19, it may not suffice to invoke the Force
Majeure clause.
On top of parties' proof that such non- compliance would not have occurred 'but
for' the Covid- 19 based event, the same event must have occurred without any of
the parties' own faults.[12] Considering that any potential lockdowns do not
count as faults of the party, such a condition may bear some comfort to parties
seeking relief. However, this is particularly relevant to certain industries
such as the shipping industry, where certain shipments can be made upon the
procurement of appropriate governmental licenses. If a party fails to simply
procure such licenses, the court may not be sympathetic to their attempt to seek
relief - as the supervening event took place because of the party's own fault.
A strong example of a case that highlighted the vitality of direct causation
between the supervening event and the non- compliance of contractual obligations
was Coombs V. Nolan, wherein the deciding court took into account the
alternative means which were available to the party seeking relief. More
specifically, the judges evaluate whether these alternative means were turned
to, for the performance of the contractual obligations. In this particular case,
the party seeking relief had attempted to acquire the commodity in regard
(horses) from localities nearby and also offered to pay twice the conventional
amount to procure horses and unload ships.
The language used in the contract would also affect its interpretation and
subsequent potential relief granted by the judges. For instance, a clause that
requires that the parties be " prevented" by the Force Majeure event will be
interpreted differently from a more direct causal link laid down in the
contract- such as " impeded" or being "hindered" in the performance of the
contractual obligations.[13]
In furtherance, it should be noted that the Bombay High Court, in
Standard
Retail Pvt. Ltd. v. M/s G.S. Global Corp & Ors.[14] did not grant an injunction
since it could not find direct causation between the pandemic situation and the
non- performance of stipulated contractual duties of the parties. In this case,
the commodity in regard was steel, which was ruled as an essential commodity
during the lockdown imposed on account of the Covid- 19 Pandemic and the
aggrieved party could not claim relief for non- performance. Interestingly, even
the ambit of working at home may not be considered a valid ground for the lack
of performance, since work can still resume- even though it might be
inconvenient.
Finally comes the question of the Covid-19 pandemic comprising an act of god.
While there exists little precedent in terms of a direct interpretation of
pandemics historically, meaning can be extrapolated from The
Divisional
Controller, KSRTC v. Mahadava Shetty[15], where it was noted that an act of God
amounts to an operation of natural forces which are free from anthropological
intervention. This unanticipated natural event cannot work as a justification
for non- performance, in case it could even be briefly anticipated.[16]
Conclusion
Force Majeure remains a legal concept which can duly save parties from
counter-productive performance of contractual obligations. Nevertheless, due to
the lack of statutory base, it can also be designated as a precarious tool, the
misuse of which would be onerous upon the courts of India to prevent. This is
also a reason as to why courts look to establish direct causal links between the
supervening event and the non-performance by parties.
Conclusively, force majeure can be established as a particularly intriguing
legal concept, when taken the public-policy context into account- primarily so,
because at least courts in India have precedentially not addressed a pandemic
situation directly.
End-Notes:
- Frederick Pollock and Dinshah Mulla, Indian Contract And Specific Relief
Acts (16th edn, Lexis Nexis 2019
- Dhanrajmal Gobindram V. Shamji Kalidas & Co., AIR 1961 SC 1285
- Dhanrajmal Gobindram V. Shamji Kalidas & Co., AIR 1961 SC 1285
- Energy Watchdog v. CERC[1954] SCR 310
- Satyabrata Ghose v. Mugneeram Bangur & Co. 1954 SCR 310
- Zarir Bharucha, 'Force Majeure And Frustration Of Contracts During COVID-19
- Coronavirus (COVID-19) - India' (Mondaq, 2020)
- Zarir Bharucha, 'Force Majeure And Frustration Of Contracts During COVID-19
- Coronavirus (COVID-19) - India' (Mondaq, 2020)
- Department Of Expenditure Procurement Policy Division & Kotluru Reddy,
Force Majeure Clause (2020).
- Department Of Expenditure Procurement Policy Division & Kotluru Reddy,
Force Majeure Clause (2020).
- Zarir Bharucha, 'Force Majeure And Frustration Of Contracts During COVID-19
- Coronavirus (COVID-19) - India' (Mondaq, 2020)
- Energy Watchdog and Ors. vs. Central Electricity Regulatory Commission
and Ors., (2017) 14 SCC 80
- Boothalinga Agencies vs. V.T.C. Poriaswamy Nadar, AIR 1969 SC 110
- Aditya Sikka, Adarsh Saxena and Drishti Das, 'FORCE MAJEURE IN THE TIMES OF
COVID -19' (Cyril Amarchand Mangaldas Blog, 2020)
- (BHC, 8 April 2020)
- The Divisional Controller, KSRTC v. Mahadava Shetty, 2003 7 SCC 197
- Adarsh Saxena, Aditya Sikka and Drishti Das, 'Force Majeure In The Times
Of Covid-19' (India Corporate Law, 2020) accessed 23 December 2020.
Award Winning Article Is Written By: Mr.Vikram Jain
Authentication No: MA214507986890-25-0522
|
Please Drop Your Comments