The Government of Andhra Pradesh (the State Government) vide its order no. G.O.Ms. No. 20 dated July 17, 2020 notified Andhra Pradesh Renewable Energy
Export Policy, 2020 (the Policy) in concurrence of Finance in
U.O.No.FIN01-FMU)ASD(IIE)/4/2020-FMU-IIEIC(Computer.No.1132369), dated, April
09, 2020.
Highlights of the Policy
- The Policy has been formulated taking into consideration the huge
untapped potential and availability of lands in the state and to encourage,
develop and promote renewable energy projects by investors for the purpose
of energy export outside Andhra Pradesh without any obligation of
procurement of power by State DISCOMs, decided to notify the Policy;
- The objective of the Policy is to facilitate, (a) 120 GW
renewable energy projects; (b) lease of 5,00,000 acres of potential land to
renewable energy export project developers; (c) attract private investment; (d)
promote setting up of renewable energy equipment manufacturing facilities in the
State; and (e) generate additional revenue;
- The Policy shall be applicable to solar / wind / wind-solar hybrid
projects for a period of 5 years with effect from July 17, 2020 during which
all registered companies either in private sector or public sector shall be
eligible for project development;
- Allocation of renewable energy resource to project developers in any
area shall be done on first come first serve basis and priority shall be
given to such developers intending to set up energy exports projects along
with manufacturing facilities in the state;
- The power generated from the projects shall be exported outside the
state and in case of supply of this power within the state, the same shall
achieved under Open Access regulations with all charges levied by A.P.
State Electricity Regulatory Commission to be paid and all connected regulations
complied with;
- Any injection of energy between synchronisation and
declaration of commercial operations date shall be treated as an inadvertent
power and no cost shall be paid by any distribution company(ies) in the state;
- State Government through a land aggregating agency will procure and
aggregate government and private lands at potential locations for allotment
to the project developers on lease basis for a period of 30 years;
- The following charges shall be paid by the project developer:
SN |
Charges |
Rate |
1 |
Annual Charges |
Rs 31,000/- per acre per year for the
lease period of 30 years with an escalation @ 5% every 2 years from
the date of possession till the expiry of the lease deed. |
2 |
Common Areas |
Lease charges for land for common
purposes (roads, substations, etc) and for unusable land (high
tension lines passing through the energy park etc.) will be to the
account of the project developer, on pro-rata basis, with an
escalation @ 5% every 2 years from the date of possession till the
expiry of the lease deed. |
3 |
Green Energy Development Charges: |
Rs 1,00,000/- per MW of installed
capacity / year for entire life of the project starting from the
date of commissioning of 1st phase of the project, with installed
capacity being assessed on AC or DC whichever is higher from time to
time. |
4 |
Annual charges paid for private lands |
Rs 25,000/- per acre per year for the
lease period of 30 years with an escalation @ 5% every 2 years from
the date of possession till the expiry of the lease deed. |
5 |
One time charges paid by project
developer |
- Local Area Development Fund: Rs 50,000/- per acre;
- Park Infrastructure Development Charges: to be collected upfront
as per Detailed Project Report;
- One time processing fee: Rs 2,000/- per acre
|
- Connections to State Transmission Utility (STU) and Central
Transmission Utility (CTU) networks:
Connection to STU
Two options have been provided to the project developers:
Option 1:
- The project developer may connect to STU by laying connecting line to the STU
grid substation at its cost and transferring the line asset to APTRANSCO prior
to commissioning;
- Alternatively, the connecting line may be built by APTRANSCO at the cost of
the project developer if it so chooses;
- Project Developers using the IntraState Transmission network shall pay for
Transmission charges and losses as prescribed by APERC in the Transmission
Tariff Order;
Option 2:
- The project developer(s) may bear the entire cost of existing or new external
evacuation infrastructure including connecting line, grid substations and
upstream network up to CTU;
- The construction of new network infrastructure shall be done under the
supervision of APTRANSCO and the assets handed over to APTRANSCO before
commissioning;
- The new network augmentation required for this purpose shall be
determined by APTRANSCO; and
- Developers opting for this option shall pay only the O&M charges as
decided by APTRANSCO and the transmission charges shall be exempted for entire life of
the project. There shall be no exemption on energy losses.
Connection to CTU
The project developers shall follow the procedure laid down by central agencies.
All liabilities on account of connecting to CTU shall be borne by the Project
Developer.
- Incentives by State Government include conversion of lands prior to the
execution of the lease agreements and apart from conversion fee for
conversion from Agriculture use to Non-Agriculture no further charges to
be levied on the park or project developer and projects will be exempted
from obtaining any consent under pollution control laws from AP Pollution
Control Board; and
- The following additional incentives shall be applicable for new
manufacturing facilities, equipment and ancillaries related to renewable
energy setup in the State:
- Priority allotment of land on long term lease basis;
- Exemption from payment of Electricity Duty for a period of 10 years from
date of commencement of manufacturing activities; and
- Extending of incentives as per the prevailing Industrial Promotion
Policies of the Government of A.P.
- If any conflict arises with existing policies, this policy shall take
precedence over the earlier policies issued in the matter.
Written By:
K Venkat Satyanarayana, Partner,
Himanshu Mene, Associate
Please Drop Your Comments