The recent judgement delivered by the Hon'ble Supreme Court of India in the
case of
South East Asia Marine Engineering and Constructions Ltd. vs. Oil
India Limited [i] assumes relevance on account of its wide implications when
it comes to setting aside arbitral awards under section 34 of the
Arbitration & Conciliation Act, 1996 (Arbitration Act). Vide this
judgment, the Supreme Court has indicated its deviation from the earlier
standard of minimal judicial interference. Safe to say this, the judgment
widens the scope of judicial interference whilst entertaining applications
for setting aside arbitral awards under section 34 of the Arbitration Act.
Factual Matrix
The appellant, South East Asia Marine Engineering and Constructions Ltd (SEAMAC)
had secured a contract for the purposes of well drilling and other auxiliary
operations in Assam. The contract contained a
change in law clause whereby
any post facto change in law causing an increase or reduction in cost to be
incurred by SEAMAC would have to be considered and reimbursed by the
parties.
During the subsistence of the contract, there was an increase in
the price of high speed diesel, a material essential for the operations
being conducted by SEAMAC under the contract. SEAMAC claimed that the
increase in price of the High Speed Diesel was on account of a change in
law and thus the Respondent, Oil India Limited (OIL) was required to
reimburse the increase. OIL refused to reimburse the demand and this led the
dispute to arbitration.
Tribunals Award
The Tribunal decided in favour of SEAMAC and allowed its claim granting it
compensation along with interest. Applying the principle of liberal
interpretation of contract, the tribunal observed that though the change in
price of the diesel by way of the circular would not be a change in law per
se, it surely had the force of law. The Tribunal held that the expression
change in law would include within itself the increase in price of High
Speed Diesel.
Challenge to the Award
OIL preferred a challenge to the award under section 34 of the Arbitration
Act before the District Court, who did not find the award to be against
public policy of India. The judge also did not find the award to suffer from
a patent illegality and thus refused to interfere. OIL thus preferred an
appeal before the High Court under section 37 of the Arbitration Act. The
High court found fault with the award and held that the Tribunal had
incorrectly interpreted the terms of the contract. The High Court thus set
aside the district Courts order and set aside the award. SEAMAC challenged
the high court's order before the Supreme Court.
Supreme Court's Decision
OIL contended before the Supreme Court that the tribunal did not take the
contract into consideration as a whole and thus failed to apply the cardinal
principle of interpretation. The Supreme Court found fault with the decision
of not only the tribunal but the High Court's as well. The supreme court
placed reliance upon its earlier judgment in the case of
Dyna Technology
Pvt Ltd vs Crompton Greaves Ltd[ii] to observe that an arbitral award
can be set aside if the perversity of the award goes to the root of the
matter without a possibility of any interpretation to sustain the award or
that the award is not permissible under section 34 of the Arbitration Act.
The court refused the wide and liberal interpretation of the contract
applied by the tribunal. Thus holding that the interpretation that was
sought to be applied tribunal was impossible, the Supreme Court refused to
interfere with the High Court's order setting aside the Tribunals award.
Analysis
The Supreme Court has thus indicated its shift from the earlier standard of
minimal judicial interference. The Supreme Court has since quite some time
now been firm in its stand that that an arbitral award may be set aside only
on grounds set out under section 24 of the Arbitration Act. The judgement
thus provides an expansive interpretation of scope of judicial interference
under section 34 of the Arbitration Act. The straight effect of this
judgement being that incorrect interpretation of contractual provisions now
form a ground for setting aside arbitral awards under section 34 of the
Arbitration Act.
End-Notes:
- Civil Appeal No. 673/2012 and Civil Appeal No. 900/2012
- 2019 SCC Online SC 1656
Authentication No: AG30671860198-3-720
|
Please Drop Your Comments