Introduction to Force majeure:
Force majeure is an occurrence of
Supervening event which not able to control or assumed by the parties, further
it is a relieve to the parties from contractual obligations. In nature these
obligations are as rights of the promisee and duties of promisor.
The relief
given to the parties are for the temporary period. Force majeure is clause which
parties agrees before making a contract and signing this clause them to bind by
the contractual obligations and relief under force majeure clause. In Indian
though terminology in the sections of Indian Contract Act, 1872. did not
prescribe
Force majeure' but doctrine is embodying or able to be seen in the
section 32 of the Indian Contract Act, 1872.
Section 31 to section 36 deals with
the Contingent Contracts, the contracts to do or not to do something is deemed
based on the event collateral to such contract. In these contract promisors is
bound to perform only after occurrence something (event, circumstances) which
are collateral to event. Illustration of section 31 where it is explained that A
agrees to Pay B only if B's house is burnt, here burning of house is an event
collateral to contract.
Now, section 32 embodies doctrine of Force majeure as it
defines that to do or not to do anything means performance of promisor is only
possible after occurrence of event and if event becomes impossible then Contract
becomes void. Basis of the section 32 are found in the Latin maxim and doctrine
of Here doctrine of Force majeure can be understood as supervening event makes
collateral circumstances of contract impossible based on which performance of
promisor depended.
Ex- In illustration of section 31, mentioned above, if due to
earthquake house of B gets collapse, then event of house getting burn is
impossible due to which collapse of house, and contract becomes void. Due to
Supervening event, possibility of performance getting impossible is already
agreed by parties in contract. But such Supervening event should not be
controlled and assumed by the parties to contract.[i]
Absence of Force majeure -As discussed above because it is parties of the
contract to oblige to the Force majeure but in cases where force majeure is not
signed by the parties in the contract then it becomes a question of fact for the
court based on the nature of the contact as it is parties to decide the relief
and performance for the promisor, here based on the nature of the contract
parties to decide whether to discharge the contractual obligation between them
under principle of frustration of contract, under section 56 of Indian Contract
Act, 1872.
Under frustration of contract where to do an act under contractual
obligations which becomes impossible due to some intervening event, which promisor could not control becomes void due to impossibility of the act. In
compare to nature of the force majeure and frustration of contract, main element
is that act become impossible' due to event which is beyond the control and
assumption of the parties. Relief to parties under is given only if performance
of the parties becomes impossible.
What is impossible is defined in the land
mark case of
Satyabrata Ghosh vs Mugnareem Bangur & Co.[ii], as impossibility
does not mean a literal interpretation but it implies two elements as:
- The Supervening event should destroy the foundation/ subject matter of
the contract and
- Thereby continuing a former contract is impractical and unreasonable
because object or purpose of the contract is already frustrated and cannot
be achieved further.
The purpose and subject matter of the contract is always a
question of fact based on the consideration parties to the contract.[iii]
Mere hardship vs impossibility of the event:
The relief under force majeure is
given on the basis of discretion of the court and relief may be declined in some
cases where there is mere hardship and not an impossibility of the event. In the
recent case during the coronavirus and lockdown, many corporate parties faced an
issue in performance of the parties. The issue as question of fact and question
of law were emerged as to whether epidemic should be covered under force majeure?
In
Standard Retail Pvt. Ltd. vs M/s G. S. Global Corp & Ors[iv], where apart
from question of fact and factual foundations of the case Bombay High court gave
a ratio decidendi as mere hardship to the parties under performance of the
contract is not covered under definition of impossibility and avoids the relief
under force majeure clause.
Mere hardship only a difficulty for parties to
perform the obligations where object and purpose of the contract is still can be
achieved through performance. Mere uneconomical/ loss to the parties is not
impossibility. So, Mere hardship is embodied to relieve parties through force majeure.[v]
Importance of force majeure-force majeure helps parties to save them from the
loss they may suffer due to external event. The importance could be understood
more from the contract in corporate sector as it faces loss mainly in the
consideration of the contract. Consideration in the corporate contracts in
mainly of expensive and significant assets. Importance of force majeure is not
only for relief but also to avoid excessive, unfair advantages to the other
party (mainly promise). To understand importance of force majeure parties should
be aware while making the list of the events to declare under force majeure.
The
parties to the contract must define the events under force majeure very
specifically because force majeure is never an open interpretation for the court
rather it is a direct, literal interpretation for the court to decide the case.
In the case:
Energy Watchdog vs Central Electricity Regulatory Commission
[vi],
Supreme court gave a ration that force majeure should interpreted strictly and
relief from performance of contract can only be given in the cases where events
which are explicitly defied under the force majeure clause. So it can be
understood that responsibility of the parties is not only to include force
majeure but also by corporate understanding to make a clear exhaustive list of
events under force majeure to get relief from the performance of contract.
Case laws: Discussing some case laws and significant ratio decidendi and obiter
dictums from Supreme court and High courts in India. In case of
Hindustan Steel
Works Construction Ltd. vs Tarapore & Co. and Ors[vii]. court held that relief
(injunction) under force majeure is given to plaintiff for reason being that in
absence of granting such relief plaintiff would have suffered irreparable harm
for eighter insistence of performance or termination of the contract. So further
though such reliefs are granted by the courts, but along with it some conditions
and guarantees need to be obliged by the parties of the contract.
In case:
Gandhi Sahakra Sakkare Karkhane vs National Heavy Engg. Coop. Ltd. and Ors[viii], it
was held that failure to meet with conditions, guarantees will be led to breach
of the contract.
In case:
The Divisional Controller, KSRTC v. Mahadava Shetty[ix],
Supreme Court held that not every natural event is covered under Act of God' to
relieve the parties from contractual obligations, relief may be decline on the
reason being presence of reasonable possibility of anticipating the threat by
parties.
In case:
Sri Ananda Chandra Behera v. Chairman, Orissa State Electricity
Board[x], the court discussed on issue regarding causation link to prove
What
is Natural Cause', general interpretation is always taken that Natural Cause
should not have any human intervention, but sometimes it is observed that human
and nature by together led to natural cause. In this case court held that in
such circumstances immediate and direct cause should be taken to determine
whether it is Act of God or Human Cause.
In case:
Nafed vs Alimeta[xi],
difference between Frustration of Contract and Force majeure was cleared as
force majeure is assumption of threat of supervening event before execution of
contract whereas frustration of contract is intervening event frustrating the
contract at the time of execution of the contract.
Court held that relief under
frustration of contract can be declined for reason being presence of force majeure in the contract. These all case laws help us to understand the
substantive and procedural aspects regarding breach of contract and damages
covered under force majeure in India under Indian Contract Act,
1872.[xii] [xiii]
End-Notes:
-
https://economictimes.indiatimes.com/small-biz/legal/what-is-force-majeure-the-legal-term-everyone-should-know-during-covid-19-crisis/articleshow/75152196.cms
- Satyabrata Ghosh vs Mugnareem Bangur & Co., 1954 AIR 44.
- https://www.mondaq.com/india/litigation-contracts-and-force-majeure/930674/force-majeure-in-times-of-covid-19-challenges-and-the-road-ahead
- Standard Retail Pvt. Ltd. vs M/s G. S. Global Corp & Ors, Commercial
arbitration petition (L) No. 404 of 2020.
- https://www.jurist.org/commentary/2020/05/tushar-behl-force-majeure-india-covid19/
- Energy Watchdog vs Central Electricity Regulatory Commission, (2017) 14 SCC
80
- Hindustan Steel Works Construction Ltd. vs Tarapore & Co. and Ors. 1966
SCC (5) 34, JT 1966 (6) 295.
- Gandhi Sahakra Sakkare Karkhane vs National Heavy Engg. Coop. Ltd. and
Ors, CASE NO.: Appeal (civil) 2952 of 2007.
- The Divisional Controller, KSRTC v. Mahadava Shetty, CASE NO.: Appeal
(civil) 5433 of 2003.
- Sri Ananda Chandra Behera v. Chairman, Orissa State Electricity Board, 1997
I OLR 390.
- Nafed vs Alimeta, Civil Appeal No. 667 of 2012.
- http://www.lawstreetindia.com/experts/column?sid=393
- https://corporate.cyrilamarchandblogs.com/2020/04/force-majeure-in-the-times-of-covid-19/#_ftnref4
Authentication No: JL30520671766-19-720 |
Please Drop Your Comments