The Supreme Court, while deciding the
United India Insurance Co. Ltd. v. Hyundai
Engineering Co. Ltd.[1](hereinafter referred to as the ‘UIIC’ Case), made a
rather surprising interpretation of the Section 11 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as the 1996 Act).
The judgment
delivered by the Apex Court overturned a previous judgment of the Madras High
Court, wherein the Madras High Court had appointed an arbitrator. In its
judgment, the Madras High Court had assessed the power of the High Courts,
especially in light of the effect caused by the Amendment to the Section 11 of
the Act by Act No. 3 of 2016.[2] In that case, the High Court concluded the
scope of its powers to be confined to merely confirming the existence of an
arbitration agreement.
The Section 11 of the 1996 Act has always met with trouble in interpretation by
the Courts, especially when the issues concerned the determination of the power
of the Chief Justice under the provision. The Bench in the case of
Konkan
Railways Corporation v. Mehul Constructions[3] opined for the first time in it,
which was reiterated in the
Konkan Railways Corporation v. Rani
Constructions[4] by a Five Judge Bench, terming the power under this section to
be an administrative one.
However, a Seven-Judge Bench decided against it, and
held it to be a Judicial Power, and it was affirmed by the Supreme Court. The
S.B.P.
& Co. v. Patel Engineering Ltd. & Anr.[5] Held the order to indeed be a judicial
one, and it was in the case of
National Insurance Co. Ltd. v. M/S. Boghara
Polyfab Pvt. Ltd.[6] wherein the topics that needed to be assessed by the Chief
Justice were decided, especially the ones that the Chief Justice must, may, or
should not consider.
However, the Amending Act had sought to alter this position laid down by the
courts. The Courts had laid down three assessments for the Chief Justice to
consider – he must assess whether the High Court so approached was appropriate,
and whether there was an arbitration agreement in existence; he may assess if
the claims before the Court are barred due to limitation; but he was not in any
situation to consider whether the claims were arbitrable or not.
The Amendment sought to alter this position with the introduction of the
sub-section 6A to the Section 11 of the Act. With the addition of sub-section
6A, the potential of the scrutiny by the High Court or the Supreme Court was
confined to the assessment for the existence of the arbitration agreement, and
not more than that. Of the three assessments laid down in the Boghara Polyfab
Case, the Amendment rendered useless the second and the third assessments that
were to be made by the High Court or the Supreme Court, as the case may be.
The UIIC Case did not present any dispute as to whether the arbitration clause
existed or not, but whether the claims that had been made fell into the scope of
the arbitration clause. In this case, by examining the arbitration clause, and
the dispute so raised, the Supreme Court delved into the issue that the Chief
Justice was never supposed to consider under the Section 11, even under the
several cases in the judicial history of the section.
If this judgment was to be
assumed to be right, then the powers of the High Court would stand expanded to
what had been held in the Patel Engineering Case. If the High Court indeed is
supposed to examine the claims that have been made and the existing disputes, it
would greatly magnify the power of the High Court, something that the
sub-section 6A vehemently intended to not allow.
This judgment by the Supreme Court will lay the impetus to several more
questions that will pose as a problem for the interpretation of the Section 11
in the cases to come. The problems that will come up will typically pertain to
the other issues that will demand consideration, especially if the UIIC case was
to be interpreted strictly. The discharge of the contract will also need to be
examined, and is one of the other problems that may present themselves, not to
mention, that the question of Arbitrability will also demand to be analysed when
the Court is disposing any application under the Section 11 of the 1996 Act.
The situation before the UIIC decision was apt – it was proper. This was because
the decision of the High Court or the Supreme Court upon the existence of the
arbitration agreement – whether it existed or not - brought along a certainty
in the situation, and for the provisions of the 1996 Act, the decision would
have been final.[7]
It would have been the proper course of conduct for the
Supreme Court to merely confine its assessment of the matters that are simply
covered under the Section 11(6A) of the 1996 Act, and then leave the rest of the
matters in the Tribunal that would be so appointed. The Tribunal may then take
its turn to assess the issue of Arbitrability.
The Amendment to the 1996 Act
ensured that the balance between the two powers – to appoint an arbitrator, and
to assess the questions of jurisdiction under the Section 16 of the 1996 Act.
The procedures mentioned here would also limit the intervention of the Courts,
in accordance with the provisions of the 1996 Act.[8] This will also enable to
eradicate any conflict when the arbitrator is being appointed, or if the
validity of the jurisdiction under Section 16 of the Act is being assessed.
The judgment of the Supreme Court in the UIIC Case will open up several other
conundrums in the law, which need to be addressed immediately. The UIIC judgment
will reopen the controversies prevalent in regards the interpretation of the
Section 11 of the 1996 Act, undeniably, from several other new perspectives.
Reinstating the position before the Amendment to the 1996 Act will pose several
other loopholes for the Courts, to which, as of now, no answer remains.
End-Notes:
- Civil Appeal No. 8146 of 2018. Available at
- https://indiankanoon.org/doc/164803491/
- The Arbitration and Conciliation (Amendment) Act, 2015, No. 3 of 2016.
Available at
- http://164.100.235.75/upload/asset/1453103622_Arbitration%20and%20Conciliation%20Act,%202015.pdf.
- Konkan Railway Corp. Ltd. & Ors. vs. M/S. Mehul Construction Co., 2000
(7) SCC 201. Available at - https://indiankanoon.org/doc/1752565/.
- Konkan Railway Corp. Ltd. vs. Rani Construction Pvt. Ltd., Appeal
(Civil) 5880-5889 of 1997. Available at – https://indiankanoon.org/doc/1999671/.
- S.B.P. & Co. v. Patel Engineering Co. & Anr., Appeal (Civil) 4168 of
2003. Available at - https://indiankanoon.org/doc/1641452/.
- National Insurance Co. Ltd. v. M/S. Boghara Polyfab Pvt. Ltd., Civil
Appeal No. 5733 of 2008, Available at - https://indiankanoon.org/doc/1243245/.
- Section 11(7), 1996 Act.
- Section 5, 1996 Act.
Please Drop Your Comments