A Precedent on Doctrine of Frustration, Force Majeure or Contingency appended
to Contract The Supreme Court of India in the matter ofÂ
National Agricultural
Co-opeartive Marketing Federation of India(NAFED) vs Alimenta SA CIVIL
APPEAL NO.667 OF 2012, put forth the grounds on which Section 32 (Contingent
contract) and Section 56 (Agreement to do impossible act) of the Indian
Contract Act, 1872 may be invoked in the scenario of non-performance of
obligation under the commercial contract by the party obligated to perform for
the benefit of other Party. Though the appeal was filed before the apex court to
decide the enforceability of the foreign award, however, the Court has also
deliberated upon the incidental question of law covering Section 32 and Section
56 of the Indian Contact Act. 1872.
Synopsis of the Case:
- National Agricultural Cooperative Marketing Federation (NAFED)
(Appellant) executed a contract with the foreign entity Alimenta SA
(Respondent) for supply of 5,000 metric tonnes of Indian HPS groundnut
(Commodity).
Â
- NAFED was a canalizing agency for the Government of India for the
exports of the commodity. For any export, which is to be carried forward to
next year from the previous year, NAFED required the express permission and
consent of the Government of India, being a canalizing agency, which was
expressly mentioned in the contract executed between Alimenta SA and NAFED.
Â
- The transaction was governed by covenants such as Force Majeure and
Prohibition contained in Clause 14 of the Agreement, whereby in case of
prohibition of export by executive order or by law, the agreement would be
treated as cancelled.
Â
- On August 1980, NAFED shipped only 1900 metric tonnes of commodity in
receipt to the first Agreement. The balance stocks of 3100 metric tonnes of
commodity could not be shipped as scheduled, due to the Government
restrictions.
Â
- This led to the allegation by Alimenta SA that NAFED committed breach of
contractual obligation and eventually the matter was decided through
arbitration, against the NAFED.
Â
- The NAFED filed an appeal with the Supreme Court, upon allowance of
application of enforcement of award by the High Court.
Key Consideration under Section 32 and Section 56 are as follows:
Section 32 of the Contract Act provides for enforcement of contingent
contracts, which reads as:
A
contingent contract is a contract to do or not to do something, if
some event, collateral to such contract, does or does not happen.
A contingent
contract is a contract to do or not to do something, if some event, collateral
to such contract, does or does not happen.
Section 32 of the Contract Act applies in case the agreement itself provides for
contingencies upon happening of which contract cannot be carried out and provide
the consequences. To this case, provisions of Section 32 of the Contract Act is
attracted.
Whereas, Section 56 of the Contract Act deals with the agreement to do an
impossible act or to do acts afterward become impossible or unlawful. It also
provides for liability of the promisor to do something which he knew or might
have known with reasonable diligence an act which is impossible or unlawful; as
such, the promisor must make compensation for the nonperformance of the promise.
However, in the present case the parties were well equipped with the fact, that
NAFED required the express permission and consent of the Government of India,
being a canalizing agency, and in any event such permission could not be
obtained due to any reason, than NAFED would not be able to perform its
obligation, however, NAFED will not be liable for any such nonperformance.
Court quoted that:
Ram Kumar v. P.C. Roy & Co. (India) Ltd., AIR 1952 Cal. 335 (338), the
High Court held:
20. Frustration depends on what has actually happened & its effect on the
possibility of performing the contract. Where one party claims that there has
been frustration & the other party contests it, the Court has got to decide the
issue 'ex post facto' on the actual circumstances of the case.
In this case,
expected event was a refusal by the Government as agreed to
under Clause 14 of the Agreement. On the happening of such an event, it is so
fundamental as to be regarded by law as striking at the root. As such, we are of
the opinion that the contract was rendered void in terms of section 32 of the
Contract Act.
Further, in the instant case the Supreme Court has observed that because of the
clear stipulation in clause 14 of the contract, it is apparent that the parties
have agreed for a contingent contract. Also, that
Section 56 is not attracted
as the promisor and promisee both knew the reason in advance as in agreement
such a contingency was provided itself in case of Government’s executive order
comes in the way, for cancellation of the contract. Thus, the contract became
void on the happening of the contingency, as provided in section 32 of the
Contract Act.
Think Tank
Section 56 deals with such contract and situation, wherein the performance of an
act by a Party was possible at the time of its execution, however, due to
occurrence of some supervening act or situation, beyond the control of either
party, which has shaken the very foundation of the contract. Whereas, the
section 32 deals with such situation where the contract itself provides for
contingencies upon happening of which contract cannot be carried out and provide
the consequences, alike present case.
In the scenario of entire nation lockdown, which led performance of contract at
halt, the obligatory party, which is default due situation prevalent in the
market, may either take a plea of Force Majeure, if the contract expressly
provides so. However, in the absence of a force majeure clause in the contract,
such party may invoke the doctrine of frustration under Section 56 of the Indian
Contract Act, 1872, provided that a contract has become impossible, and the
arrangements and conditions have become entirely different from those envisaged
in the contract.
Hence, while deciding upon which provisions or doctrine to be invoked on
occurrence of any such situation, wherein the performance of obligation become
impossible, the parties should carefully evaluate the situation and available
remedies thereto.
- Title : National Agricultural Co-opeartive Marketing Federation of India
(NAFED) vs Alimenta SA CIVIL APPEAL NO.667 OF 2012
Link to the judgement: https://indiankanoon.org/doc/155215460/
Disclaimer
The contents of this article should not be construed as legal opinion. This
article is intended to provide a general view on the subject matter. Specialist
advice should be sought about your specific circumstances. We expressly disclaim
any financial or other responsibility arising due to any action taken by any
person on the basis of this article.
 Â
Please Drop Your Comments