File Copyright Online - File mutual Divorce in Delhi - Online Legal Advice - Lawyers in India

Interim Arbitral Reliefs in determinable contracts

In the realm of Jurisprudence it has been said that Possession is 9/10 of the Law. It can be said that similar is the case of Interim Relief's in the case of Arbitration, both before the National Courts and before the Arbitral Tribunal the above mentioned quotation holds all the more true as in the 21st Century arena of minimum interference in the Arbitral Process , with the role of the National Courts becoming vapid , it is the seeking of interim relief's which the National Courts have found themselves circumscribed to in today's era.

The seeking of Interim Relief's in the case of determinable contracts containing an arbitral clause is commonplace, even though the chances of success are limited due to the obstacles placed by The Specific Relief Act 1963 and other allied Legislations.

The General Law with regard to the seeking of Interim Relief's in a determinable contract was settled in the case of Indian Oil Corporation vs Amritsar Gas Service [1] wherein the Apex Court held that a distributorship agreement which had a clause which entitled either party to terminate the contract with 30 days prior notice and without assigning any reason was determinable in nature and could not be specifically enforced .

This short Article will attempt to elucidate the bars to seeking interim relief through the prism of The Arbitration and Conciliation Act, 1996 in cases of determinable contracts and will also endeavour to understand if there are any exceptions to this rule as the seeking of Interim reliefs in case of determinable contracts is usually stymied by the provisions of The Specific Relief Act 1963.

II. The meaning of Determinable Contract:

Determinable Contracts derive their existence from the termination clause envisaged therein. The word determinable used in Clause c to sub-section 1 of Section 14 of The Specific Relief Act, 1963 means that which can be put an end to. Literally the word determinable means to put an end to.

III. The approach of the National Courts when dealing with a Section 9 application under The Arbitration and Conciliation Act, 1996 in case of determinable contracts:

We shall analyze the approach of the National Courts in Section 9 Petitions preferred under The Arbitration and Conciliation Act, 1996 in case of determinable contracts through Judgements of the Delhi High Court and Apex Court as enumerated below.
  1. M/S Inter ADS Exhibition Pvt Ltd v/s Busworld International[2]:
    In this the Petitioner and the Respondent had entered into a Joint Venture Agreement to jointly organize an event known as Busworld in Bangalore . The Respondent after the successful completion of the event terminated the JVA with the Petitioner herein. The Petitioner filed an application for Interim Relief in the Delhi High Court under Section 9 of The Arbitration and Conciliation Act, 1996 praying that the Respondents be restrained from terminating the Joint Venture Agreement with the Petitioners herein. The Court concluded that as per Article 7.3 of the Joint Venture Agreement either party can terminate the agreement, hence the contract is of determinable nature.

    The Delhi High Court referred to the case of RPS Educational Society vs Stroh Brewary[3] where the Apex Court had remarked that in cases of determinable contracts, specific performance of determinable contract is statutorily barred under Section 14(1) d of The Specific Relief Act 1963 and also under Section 41(h) which says that injunction will be refused when there is an equally efficacious relief available to the parties. On the basis of this decision the Court declined to give relief to the Petitioner and dismissed the application for Interim relief preferred by them.
     
  2. Parasoli Motors v/s BMW India Pvt Ltd[4]:
    The Respondent entered into an agreement with the Petitioner for the sale of its cars in Gujarat. The Petitioner claimed before the Court there was a mutual understanding with the Respondent that the dealership would be renewed on a yearly basis. The Respondent due to the Petitioners inability to meet their yearly targets terminated the said dealership in the year 2018.

    The Petitioner filed an application under Section 9 of The Arbitration and Conciliation Act, 1996( due to the arbitration clause in the dealership agreement) seeking to restrain the Respondents from terminating the said dealership as it was their contention that huge expenditure had been made by the Petitioner to promote BMW in Gujarat , and unilaterally ending the contract would cause huge hardship to them, which cannot be monetarily compensated.

    The Delhi Court referred to the case of Planet M. Retail vs Select Infrastructure Pvt Ltd[5] wherein a Division Bench of the Delhi High Court refused to restrain the termination of a License Deed on the grounds that the License Deed entered into between the parties was terminable in nature and hence Injunction could not be granted due to the statutory bar under Section 14 and Section 41 of The Specific Relief Act, 1963. Thus the Court declined to give relief to Parasoli Motors and did not restrain BMW India from terminating the said Agreement.

    The above two Case Laws illustrated elucidate the approach of the National Courts in dealing with Interim Reliefs in case of determinable contracts. Thus it is quite lucid that the National Courts are loathe to grant Interim Relief in case of determinable contracts . We shall endeavour to understand through the next Case Law whether there is a possible exception to this rule and if so in what kind of circumstances does it arise?
     
  3. Danieli Corus Bv v/s Steel Authority Of India[6](An Exception to the rule?)-The Petitioner and the Respondent entered into an contract for setting up an Blast Furnance at Rourkela Steel Plant. The Petitioner shared technical drawings related to the Blast Furnance with the Respondent. The drawings where in the nature of confidential information and where only to be used for the purpose of the execution of the project.

The Petitioner claimed that the Respondent had uploaded the confidential drawings of the Petitioner on a 3rd party website . The Petitioner also filed an additional affidavit before the Court wherein it was affirmed that the Respondent had floated a tender for Operational Tyres and the drawings of the Petitioner where copied. In the light of these circumstances the Petitioner preferred an application under Section 9 of The Arbitration and Conciliation Act, 1996 to restrain the Respondents from further disclosing or disseminating confidential information to 3rd parties.

The Respondent in reply to the said application contended that this was a determinable contract for which no injunction could be granted and damages where sufficient to compensate for the breach in contract.

The Court referred to the case of John Richard Brady vs Chemical Process Equipment's[7] where the Court invoked General Equity of Breach of Confidence and restrained the Respondents from disclosing technical drawings as the Court was of the opinion that such conduct was a breach of confidence and amounted to unauthorized use of labour.

The Court also referred to the case of Zee Telefilms vs Sundilal Telecommunication[8] where the Bombay High Court had restrained the Respondents from disclosing confidential information even though the Contract between the parties was determinable in nature, as the Court was of the opinion that monetary compensation would not be sufficient to remedy the breach, and hence Injunction was granted to the Petitioner.

Finally the Court made a reference to the case of Daljeet Titus vs Adebar and Ors[9] where it was remarked Court will step in and grant Injunction even in case of determinable contracts to prevent a breach of confidence.

After analysing all the above Case Laws the Court restrained the Respondents from disclosing the drawings to 3rd parties, and opined that damages would not be sufficient to remedy this breach of confidence. Furthermore the Court said that once a party has obtained information on the basis of contractual terms it cannot turn around and question the confidentiality of this information. It is estopped from doing so.

Conclusion:
The above mentioned Case Laws help us understand the Judicial intricacies which the Courts grapple with in regard to granting of Interim Relief in Determinable Contracts. The Courts usually do not interfere on account of the statutory bars provided under the Specific Relief Act, 1963 however if there are extenuating circumstances like monetary compensation not being sufficient for the breach as also provided in Section 38 of The Specific Relief Act, 1963 and to prevent a breach of confidential information obtained through a contractual relationship as enumerated through the above Case Laws the Courts will grant Injunction in case of Determinable Contracts also.

End-Notes:
  1. 2013 9 SCC 32
  2. 2012 (DLT) 552
  3. AIR 2002 SCC 2598
  4. 2018 (DLT) 753
  5. 2004 (DLT) 321
  6. 2017 (DLT) 423
  7. 2016 EWCA CIV 14444
  8. 2003(27) PTC 457(BOM)(DB)
  9. 2006 SCC ONLINE DEL 551

Law Article in India

Ask A Lawyers

You May Like

Legal Question & Answers



Lawyers in India - Search By City

Copyright Filing
Online Copyright Registration


LawArticles

How To File For Mutual Divorce In Delhi

Titile

How To File For Mutual Divorce In Delhi Mutual Consent Divorce is the Simplest Way to Obtain a D...

Increased Age For Girls Marriage

Titile

It is hoped that the Prohibition of Child Marriage (Amendment) Bill, 2021, which intends to inc...

Facade of Social Media

Titile

One may very easily get absorbed in the lives of others as one scrolls through a Facebook news ...

Section 482 CrPc - Quashing Of FIR: Guid...

Titile

The Inherent power under Section 482 in The Code Of Criminal Procedure, 1973 (37th Chapter of t...

The Uniform Civil Code (UCC) in India: A...

Titile

The Uniform Civil Code (UCC) is a concept that proposes the unification of personal laws across...

Role Of Artificial Intelligence In Legal...

Titile

Artificial intelligence (AI) is revolutionizing various sectors of the economy, and the legal i...

Lawyers Registration
Lawyers Membership - Get Clients Online


File caveat In Supreme Court Instantly