The COVID-19 pandemic struggle is still on with a bleak chance of things coming
to normal in the near future. The business operations, as a result are facing
unprecedented disruptions due to the break in the supply chain giving effect to
their inadequacy in maintaining customer agreements. The arbitrariness in the
longevity of this pandemic has made the corporations to assess their as well as
counter parties rights, obligations, remedies as entered into under the contract
where the performance is delayed or becomes too difficult to perform in the
given situation.
In this light, the concept of Force Majeure comes into picture to rescue the
parties from performance in such difficult time.
This article will give an understanding on the concept of force majeure, general
provisions in the legislation, specific provisions in the force majeure clause,
invoking the cause in the contemporary situation with substantial precedents.
Concept of Force Majeure
Force Majeure is a French term which means ‘Superior Force'. The Black Law
dictionary defines the term as ‘an event or effect that can be neither
anticipated nor controlled'. Upon reading, it can be understood that force majeure
can be:
- An act of God such as earthquake, tsunami, flood, epidemic, pandemic,
etc.
- Human initiated events such as war like situation, labour unrest,
lockouts, etc.
Thus the scope of force majeure is wide enough to cater any event which portrays
the incapacity of the parties to a contract because of the unforeseeable
circumstances that cannot be controlled. In this regard it can be mentioned that
Central Electricity Regulatory Commission had, in the year 2016, held
demonetisation as a valid threshold to invoke force majeure clause entered by
the parties. This decision goes against the one taken by Honourable Supreme
Court in Energy Watchdog v CERC [1] where the scope of force majeure was kept
strictly narrow.
Force Majeure is an exception to what may be otherwise a breach of contract as
the main aim is to save the parties from invoking breach of contract which may
have been done in case of non-performance.
Force Majeure in Indian Contractual Jurisprudence
The term
force majeure is absent in its skeletal form, however, upon
interpretation, it is placed under Sections 32, 56 and 65 of The Indian Contract
Act, 1872.
Section 32 states that contingent contracts to do or not to do anything if an
uncertain future event happens, cannot be enforced by law until and unless that
event has happened. Such contracts become void if the event becomes impossible.
Thus it can be said that where there is a force majeure clause in the agreement
or a similar clause to that effect, Section 32 will be applicable.
Section 56 deals with the underlying
doctrine of frustration. It says that
where a contract becomes impossible, unlawful, or by reason of any event which
the promisor could not prevent, it becomes void when the act becomes impossible
or unlawful.
Section 65 provides the remedy where a party has received any advantage under a
contract that subsequently became void under section 56, which is:
- To either restore the advantage received, or
- To make compensation for the advantage received
Though there are provisions and the applicable remedies, however there may be
issues between the contracting parties regarding resolving disputes on the
manner and mode of payment of the compensation, expenses incurred if any,
compensation on service performed, etc. and in this light arises the importance
to incorporate force majeure clause in the contract when made.
Importance of Force Majeure Clause in the prevailing situation
Force Majeure clauses are basically mentioning the set of circumstances under
which contract performance will be either excused or delayed or any other
consequence as agreed. The force majeure clause can be made as descriptive so as
to ameliorate the protection to the parties and reduces any ambiguity where a
party feels that the counter party is evading its performance unreasonably. In
the case of
Philips P.R Core, Inc.[2], it was held that The main objective of
force majeure clauses is to relieve the parties from its contractual obligations
where the performance has been prevented by a force beyond its control or where
the purpose of contract is frustrated.
There are a few considerations that can be kept in mind while crafting the
clause amidst the pandemic.
Few of them are discussed as under:
- Inclusion of the list of events to be covered: It can be done by
way of listing expressly the events which can trigger the clause or keeping
it general by following ejusdem generis. The parties mutually agree upon this and
it is needless to say that the language is very important whether it indicates
the list as exhaustive or generic. In the case of Tandrin Aviation Holdings
Ltd.[3], it was held that Where a clause contains non- exclusive list of events,
followed by general language such as ‘any other cause beyond party's
control', to fit within its general wording, must be of similar nature to
the specified events listed.
Let us consider the current scenario i.e. Covid-19. Where the clause expressly
mentions pandemic amongst the list, it will automatically get covered,
otherwise it would depend on the facts of the case and whether the event hampers
the performance, which is again subjective.
Â
- Effect on the Contract: It is to be seen whether the event can
hinder the performance of the contract in entirety or partly or can prevent
the performance. The clause must be drafted to decide the possibilities i.e.
termination of contract or deferring it for some specific period. The clause
must also cover situations such as where the payment or performance is
partly carried out.
Â
- Burden Of Proof: The burden is on the person claiming the event
as force majeure. While establishing the event as force majeure, it can be claimed
that the event was unforeseeable, beyond the control to control the execution.
This is a critical part as the proving is difficult.
Â
- Dispute Resolution: The clause may provide for any arbitration
provision or litigation where there are unresolved disputes.
The importance of the force majeure clause can also be felt where the parties
entering into a contract or the place of performance is a civil unrest area or
which has extreme weather conditions, labour strikes, etc.
Force Majeure: When Invoked
The Courts generally satisfy themselves about when to invoke the clause after
analysing and reviewing the following:
- The precise language in the clause.
- Evidence which establishes that the event was unforeseeable when the
contract was entered.
- Nexus between the event and the non-performance by the parties due to
the happening of the event.
- Evidence which establishes that the event was of such nature that
performance could not be performed.
- Whether the performance can be made in an alternative manner.
The International Chamber of Commerce (ICC) also provides for the underlying
test that the required party invoking the force majeure clause needs to prove
which is as follows:
- That the event is beyond the party's control.
- The event could not have been foreseen when the contract was entered.
- The effects of the impediment could not have been avoided by the party.
ICC states that, where the party invokes the clause after giving timely notice,
the party can be relieved of obligations and can do away with the liability for
breach of contract. Also, the ICC Model Force Majeure Clause, 2020 provides
that plague and epidemic are examples of presumed impediments and hence the
party only needs to prove that it could not have been avoided or overcome.
Events not considered as Force Majeure
There can be situations where the performance of the contract is possible
however with bearing high cost or gaining less profit than intended and what
would have been received otherwise sane the presence of the force majeure. The
parties may argue that the performance is impracticable due to the involvement
of risk of injury to either or both the parties or to their property which is
disproportionate to the ends which will be achieved by the performance. Such
arguments are not tenable and hence the events cannot take the blanket of force
majeure event.
There are judgements to substantiate this concept, couple of them
being discussed under:
In the case of
Dorn v Stanhope Steel, Inc.,[4] it was observed that,
Impracticability means more than impracticality. A mere change in the degree of
difficulty or expense due to such causes as increased wages, prices of raw
materials, or costs of construction, unless well beyond the normal range, does
not amount to impracticability since it is this sort of risk that a fixed-price
contract is intended to cover.
In
Transatlantic Financing Corp. v. U.S,[5] the Court of Appeals affirmed that
there was no impracticability where a party sought to recover damages only
because its wheat shipment was forced to be re-routed due to the closing of Suez
Canal. It was held that, because the contract was not rendered legally
impossible and it could be presumed that the shipping party accepted some
degree of abnormal risk, there was no basis for relief.
Therefore it needs to be understood that even if the parties assume such
situations to fall under force majeure and include them in the clause, they
cannot receive any relief and their non- performance will be considered as
breach of contract.
Insisting on what can be considered as force majeure, Honorable Supreme Court,
in the matter of
Satyabrata Ghose v. Mugneeram Bangur & Co.,[6] held that:
The term
impossible has not been used in Section 56 to mean physical or literal
impossibility. A mere impracticality of performance, from the view point of
parties, and considering the object of agreement, will also be covered.
Subsequently in
Naihati Jute Mills Ltd. v. Hyaliram Jagannath.[7] Supreme
Court held that, A contract is not frustrated merely because circumstances in
which it is made is altered. Courts, in general have no power to absolve a party
from performance of its part of contract merely because performance has become
onerous on account of unforeseeable turn of events.
Conclusion
The foreseeability of Covid-19 is subject to debate. Where some argue that the
pandemic is
inevitable' but
quite unpredictable and can hence be counted in
the category of force majeure events, Counter views are that the SARS outbreak
in 2005 could make such epidemic and pandemic as foreseeable and to be
contemplated in the contract.
The Ministry of Finance issued an Office Memorandum dated February 19, 2020
which effectively states that Covid-19 outbreak is covered under Force Majeure
as it is a natural calamity, however due procedure is to be followed while
invoking the clause. This cannot be applied stringently for every contract as
the performance of every contract needs to be assessed independently considering
its nature, type of obligations, etc. and in that case the parties need to
interpret before invoking the clause.
In my view, the absence of the force majeure clause cannot take away the rights
of the parties, but limit the protection to the extent of the application of
Section 32, 56 and 65 of The Indian Contract Act. Where there is a clause
incorporated, it adds to the protection of the parties, provides clarity as to
the enforcement of the contract, the events to be covered, the compensation
manner, whether there can be an option to delay the performance without any
adversity, amongst others.
Also upon reading, it can be said that the future of
all contracts hit by force majeure cannot be termination. For instance, where X
and Y enters into a contract for the sale of furniture to be executed on
25th March, 2020. The Covid-19 situation will not allow the parties to perform
it on the scheduled date, but instead of termination, the parties can defer the
sale for some specified period.
There can be seen a flurry of disputes and litigations once the parties start
invoking the clause. Force Majeure and its application would have to be then
looked individually at the stage of arbitration or litigation. There must be
ample proof, however to show that there were no alternatives available for
performance to the parties under the contract.
End-Notes:
- Energy Watchdog & Ors. v. Central Electricity Regulatory Commission &
Ors., ((2017) 14 SCC 80)
- Philips P.R Core, Inc. v. Tradax Petroleum Ltd., 782 F.2d 314, 319(2d Cir.
1985)
- Tandrin Aviation Holdings Ltd & Aero Toy Store LLC & Others [2010] EWHC 40
- Dorn v. Stanhope Steel Inc., 534 A. 2d 798, 586 ( Pa.Super.Ct.1987)
- Transatlantic Financing Corp. v. U.S 363 F.2d 312
- Satyabrata Ghose v. Mugneeram Bangur & Co. 1954 SCR 310
- Naihati Jute Mills Ltd. v. Hyaliram Jagannath, 1968(1) SCR 821Â