In India, damages are a vital component of contracts. A strong damages framework
must allow the opposite party to recoup its losses in the event that one party
breaks its end of the agreement. The Indian Contract Act, 1872[i], a piece of
colonial-era law that still influences contemporary contractual duties, is at
the centre of the conversation. The provisions of the Act, in particular
Sections 73[ii] and 74[iii], provide a strong foundation for handling damages
resulting from construction contract violations.
While Section 74 outlines the
crucial distinction between penalties and liquidated damages, a concept of
utmost importance in the construction industry. Section 73 represents the
essential premise of guaranteeing equality by compensating the non-breaching
party for losses suffered. The study carefully analyses the subtleties of these
portions, referencing legal precedent and scholarly discussion. It draws
attention to the many factors that must be taken into account when determining
if predetermined pay is acceptable, whether damages are predictable, and how to
strike a balance between encouraging prompt performance and applying penalties.
The Contract Act substantially differentiates among compensatory and liquidated
damages.
The goal of compensatory damages is to recover the injured party's
sense of totality by recouping actual losses from the violation. This could
involve indirect losses like lost revenues in addition to direct costs like
extra labour or materials. It is both an art and a science when determining
these, and Indian courts use techniques like the 'cost of cure' or 'loss of
profits' according to the circumstances.
Conversely, liquidated damages are a
predetermined amount stipulated in the contract for particular violations such
as delays. These clauses provide certainty, but caution is necessary because
liquidated damages that are interpreted by the courts as a 'penalty' rather than
an accurate estimate of losses will be struck down. The research sheds light on
the practical application of these legal principles in actual construction
conflicts through a thorough analysis of seminal case studies.
Introduction
In India, the contracts are tested on the edifice of the Indian Contract Act,
1872 (the Act). It acts as the foundation of Since, it was enacted during the
regime of the Britishers in the colonial rule, it regulates the formation,
performance, enforcement and breach of contracts in myriad sectors. Before this
exhausting law encompassing almost everything under the sun about contracts was
enacted, the contractual relationships were governed by the personal laws of
different religious communities, which lead to disparity between the parties.
The Act has a sum total of 238 sections which are drawn heavily from the English
common law concepts while adhering to local conventions and practices. It
defines a contract as 'an agreement enforceable by law'[iv], wherein one party
extends a proposal to the other, who accepts it and thus, the parties exchange
promises with valid consideration and an agreement is arrived at. Once, this
agreement gets the seal of law, it becomes a contract. There are some essential
elements of a contract such as proposal[v], acceptance[vi], consideration[vii],
lawful object[viii], and competency of parties[ix], which are scrutinized for
the validity of a contract, this is emphasized by Section 10 of the Act.
The Act
recognizes primarily three genres of contracts, namely, valid, voidable and
void. Additionally, it lays down different types of contracts such as bilateral,
unilateral, express and implied. Another pivotal provision of the Act is
regarding the performance of contracts. The obligations that the parties are
required to perform will be done so following the specifications of Section
37[x]. Failure to such performance may lead to a breach of contract and this
gives the non-defaulting party a right to remedies like damages or an order of
specific performance.
Overall, the Act, forms the cornerstone of contract law in India, giving
contracts an elaborate structure for their creation, enforcement and fulfilment.
Its laws continue to influence economic dealings and legal issues throughout the
nation by fusing English common law ideas with native practices. It is evident
how the structure has proved robust and has stood the test of time – over 150
years. Even if certain elements have been modified to reflect contemporary
culture, the fundamental ideas are still applicable and serve as a framework for
many business dealings throughout India.
This article specifically deals with the damages in construction contracts in
four parts. The first part deals with the kinds of damages and legal provisions
relating to damages under the Act. Part II deals with the damages in
construction contracts specifically at length. Part III deals with the case
studies of the relevant study and lastly, Part IV deals with the challenges,
bandwagons and plausible solutions with respect to damages in construction
contracts.
Types of Damages in the Act
It is important to precisely define the term damages to classify it and with
reference to the case of an injured party it means the monetary compensation for
the loss suffered. The injured party plays the role of burden and responsibility
to prove his loss to the injured party. Remedies that are available when a party
has been offered to be put in a worse position due to breach of a contract
include the right to sue for compensation.
It is the reparation in money or in
kind which is claimed by the party from the other side for the loss or the
injury which the law aims to redress. There are two possible ways to cause
damages: incidental or consequential. As required by law, the estimated amount
should match the harm or detriment experienced by either party. [xi]
- General Damages
General damages are referred to as those damages that flow as a direct
consequence of the breach and are a usual aftermath of the particular breach
that occurred. A further restatement of this is that, the defendant is
answerable for all the occurrences that must precede or follow the violation, as
the circumstances of life take their natural course.[xii]
Illustration - Mr. X and Mr. Y sign a contract wherein Mr. X promises to sell
Mr. Y his 7 kg mango for Rs. 200 the following month. When Mr. X is unable to do
so, Mr. Y purchases a 5-kg mango from Mr. C for the sum of Rs. 400. In this
case, Mr. Y can sue Mr. X for the Rs. 200 he lost because he paid more for Mr.
C's mango and suffered losses as a result of A's breach of contract.
- Special Damages
Special damages are those that result from unique situations. They emerge from
the occurrence of a unique incident that causes loss or harm rather than from a
violation of the terms and conditions of the contract. In this case, the party
who violates the contract and causes loss due to unusual circumstances must make
good on their obligations by paying compensation.[xiii]
Illustration - For an agreed-upon expense, Mr. X promised to deliver a specific
object to Mr. Y. Here, Mr. Y notified Mr. X that his company is closing because
he doesn't have that certain article. However, Mr. X here doesn't deliver it on
time, which causes Mr. Y to lose a lot of money. In this case, the product
delivery contract governs the relationship, and the harm done does not result
from a contract violation. Yet, Mr. X is responsible for making up Mr. Y's loss
in this unique situation, which resulted from Mr. X's failure to produce the
article on time.
- Compensatory Damages
These awards, known as actual or compensatory damages, seek to restore the
injured party or place the guilty party in the position that he would have been
if the contract was not breached. These damages seek to provide for the value
which was lost due to a breach of contract. Some of the principles that define
the compensation award includes that the injured ought to be placed in the same
financial position as he or she would be if the other party had honoured his or
her obligations.
In regards to this concept, the damages would have to be
evaluated at the time of the breach, where the contract is that of sale. When
enforcing a contract of sale of goods, legal remedies for a breach of contract
are the difference between the contract price and the market price on the date
of breach. In the event that the seller fails to execute or deliver the contract
in accordance with its terms and conditions, the buyer may request for recovery
of the expenses incurred in obtaining the same or similar goods.
Under construction contracts, compensatory damages may include: This is easily
quantifiable immediate often expected consequences of the infraction; cost
caused by late submission, additional cost incurred in completing the work, and
lost revenue. Special losses are those losses that occur as offenses of the
breach; examples of such losses are lost commercial chances, loss of reputation,
and expensive financing.
- Liquidated Damages
Sometimes, the contract entails some fixed amount of money that should be paid
in the event of breach of some provision; the complaining party gets compensated
to that extent regardless of whether or not they suffered any loss or damage due
to the breach. If there is a condition in the contract regarding a specific sum
which is to be paid as a penalty then reasonable damages which are not more than
the stipulated amount must be awarded.
In construction contracts for instance, there are cases where clauses for
liquidated damages are inserted for purposes of resulting from one party's delay
or any other form of breach of contract. They stipulate the amount of money a
party, which has violated an agreement, will be liable to pay the other party,
following the particular violation.
The compensation clause assumes significant importance in construction contracts
as it plays a number of roles and provides distinct benefits. First of all, the
party that is in breach of the agreement knows that there are financial
consequences of not implementing the part of the agreement that was agreed upon
and thus acts as a deterrent to any delays or failure to implement the agreed
intent of the contract. It can help reduce disruptions and potential
vulnerability to cash flow impacts for the non-breaching party by mitigating
delays with respect to projects' completion.
Penalty clauses provide the
aggrieved party a proportional and equitable remedy against the contract
default, and this commonly practiced remedy is known as liquidated damages
clause. Should a violation occur, the assessment of actual damages is often a
complex process, and the award may indeed be unpredictable averting lengthy
legal proceedings. This eliminates the need for one of the parties to have to
prove real losses in court by writing a stipulation that states a particular
value in the contract. To have a compensation awarded the injured party there
has to be a legal harm that the tender has caused him.
In India, the provision where that can happen is traced from Section 74 of the
Act which addresses the issue concerning liquidated damages. As provided under
Section 74 in the event that there is a breach to the contact the injured part
shall be entitled to reasonable regain compensation not exceeding the amount of
the contract price set in the liquidated damages clause if any.
There can be no
award of any compensation if there is no legal injury to the party It would be
pertinent to note that in the absence of legal injury there can be no question
of any compensation being awarded. In another case of
Haryana Telecom Ltd. v.
Union of India[xiv] the sum granted by the arbitrator for aggravated loss on
account of breach was not sustainable since no loss was suffered where a
contractor failed to supply cables which caused the government to purchase them
elsewhere for a lower price.
Calculation methodologies as per Indian law
The Act and other decisions setting guidelines on the assessment of contractual
damages applies to assessment of compensatory damages in construction contracts.
The ones that are frequently utilized are as follows:
- Difference in Value Method: This approach involves calculating the difference between the agreed-upon cost of the work and its actual value as performed by a party that is in default. This discrepancy may be awarded as damages to the affected party.
- Cost of Cure Method: This method incorporates the cost of correcting defective works or finishing incomplete works into the calculation of damages. This covers, among other costs, the labour and supplies needed to fix the breach.
- Loss of Profits Method: The party that was wronged may seek damages for lost profits in situations where the contract violation caused a loss of projected earnings. By using this strategy, the party must show that the projected earnings are fair.
- Reliance Damages: These damages are given to make up for the expenditures incurred by the party that was wronged in relying on the contract, including recruiting staff, mobilization charges, and material procurement costs.
Three principles are applied in the computation of compensatory damages:
reasonableness, the standard of care that the defendant owed the plaintiff, and
causation by a foreseeable act of the defendant as well as mitigation of loss.
Whenever the injured party failed to act in reducing the loss, the amount of
damages they are to be awarded will be reduced.
Construction Contracts
A construction contract, on the other hand, refers to a special contract whereby
a party agrees with another party to undertake the construction of an asset or a
bundle of assets that are although not necessarily integrated in terms of
design, technology or function or intended use may be deemed to be integrated in
the building process. When the work laid down involves constructing one piece of
asset including a bridge, building, dam, pipeline, road, ship or tunnel a
construction contract can be negotiated.[xv]
A construction contract may also
cover the building of several assets that, in terms of their ultimate purpose or
use, design, technology, and function are closely connected or interdependent;
contracts for the building of refineries and other sophisticated pieces of
machinery or equipment are examples of such contracts. There is a precise method
for figuring up the income and outlays when it comes to building contracts.
The
percentage of contract completed method is the accounting technique used in
recognizing income and costs based on the work done or the amount completed to
date. Hence yields the revenue, expense and profit which may be associated with
the revenue and the cost incurred for the part of the contract accomplished
under the matching principle which is income from the contracts with the cost
which co-relates with the stage of completion of that contract.
This method is
quite helpful in establishing the amount of contacts by their activity and
performance level in a given period.[xvi] The importance of damages in
construction contracts can be ascertained from the fact that the recognition of
expected losses is ascertained through a specific procedure, which states that
in the event that it is likely that the overall contract expenses will surpass
the whole contract revenue, the anticipated loss must be promptly recorded as an
expenditure.
The calculation of such a loss is made regardless of the following factors:
- whether or not work has started on the contract;
- the extent to which contract activity has been completed; or
- the anticipated profit from other contracts that are not considered to be one single construction contract.
Legal Remedies for Damages in Indian Construction Contracts
Compensation for breach of contract is covered by Indian law in Sections 73 and
74 of the Act. The tenets that form the basis of the damages are established by
these provisions. Section 73 addresses actual damages resulting from a breach of
contract and the harm caused by that breach; these damages are considered
unliquidated damages because the courts award them based on an evaluation of the
harm or loss inflicted upon the party against whom the breach occurred. In
contrast, Section 74 refers to liquidated damages, which are damages that are
predetermined.
Therefore, a contract violation is required in order to pursue
damages claim.
In India, by bearing in mind the Specific Relief Act 1963[xvii], causes of
action for the breach of contract may be claimed. First, the provision vests the
option to require specific performance in the party instituting the suit or the
plaintiff. This takes the place of the long-standing common law principle that
stipulates that the court may award specific performance as a remedy in the
event that monetary damages are deemed insufficient. Furthermore, substituted
performance is an option available to the party bringing the lawsuit if it
decides against forcing the other party to fulfil its end of the bargain. A new
type of relief offered by the act is called substituted performance.
It states
that if either party fails to perform under the terms of the contract, the
affected party may choose to guarantee substituted performance through his own
agency or a third party of his choosing. The statute gives the court the
authority to call in technical experts to help with particular suit-related
matters. The expert might also be asked to present proof, such as delivering
relevant documents. Experts are nearly always used in complex construction
disputes, whether the issue is related to delays, quantity, design, or another
issue. It also specifies how lawsuits filed under the legislation must be
resolved within a year of the defendant receiving a summons.
The parties and the
court would be under pressure to move quickly due to the set deadlines. In
addition, the statute creates special tribunals for contracts pertaining to
infrastructure projects. These specialist courts would be better equipped to
comprehend issues pertaining to infrastructure projects, taking into account the
unique characteristics of the industry. The act modifies compensation's status
as a remedy. The modification stipulates that the party bringing the
specific-performance lawsuit must request either substituted performance or
specific performance.
Unlike the prior provision, which allowed compensation as
an additional or substitute remedy at the court's discretion, compensation may
now only be given as an additional remedy to particular performance. This is
significant because, in addition to a remedy of specific performance,
compensation is now offered because the alternative remedy was insufficient to
compensate the party filing the lawsuit for its indirect losses.
Case Studies
In the 2015 case of
Kailash Nath Associates v. Delhi Development
Authority [xviii], The Indian apex court delivered its judgment on a number of
issues concerning claims of loss of profits under a construction contract. The
court held that Kailash Nath Associates which was the aggrieved party could
recover more than its actual expenditure but also what it would have earned in
term of profit from the performance of the agreement. For calculating
compensatory damages, the court adopted 'loss of profit' method.
In
Universal Pvt. Ltd. v. B. E. Bilimoria & Co. Ltd.[xix], the court refuted the
application to challenge the award the arbitral judgment. This they said had
been done in spite of the fact that liquidated damages had been awarded although
there was no proof or any evidence of losses or damages in the first place. The
fact will be that, in order to prevent the compensating party for a breach of
the contract from deriving any profit out of it or which may be considered
unfair, that is being unjust enrichment or receiving what he has not worked for,
the courts must concede other facts and circumstance such as loss mitigation,
the reasonableness of the amount as well as other facts. This is especially
eminent where there is a specified amount contractually agreed between the two
parties as liquidated damages.
A seminal case on compensatory damages in construction contract disputes is the
Supreme Court of India's decision in
Maula Bux v. Union of India [xx]. The case
stemmed from a construction contract disagreement between Maula Bux, a private
construction firm, and the Government of India. Maula Bux had signed a contract
with the Government to build a bridge. However, during the project's execution,
the company faced substantial delays and changes in the scope of work due to
the Government's failure to provide timely clearances, approvals, and
modifications to the project requirements.
Maula Bux had significant additional
costs as a result of these modifications and delays, including higher labour,
material, and overhead costs. In addition, the business lost out on expected
earnings that it would have received had the contract been carried out without
incident or modification. Maula Bux, therefore, sought the Government
compensation for the losses it had incurred due to the violation of the
above-mentioned contract. The Supreme Court of India heard arguments on two main
points: First, whether Maula Bux may obtain an award equivalent to compensatory
damages where the Government breached the contract and second, in such a case,
the amount of damages payable to Maula Bux.
The Supreme Court ruled the favour
of Maula Bux and provided a judgment that the business was eligible to get
compensatory damages due to the Government's violation of a contract and the
resultant losses. First, Maula Bux was compensated for additional costs incurred
as a result of delays and modifications in the scope of work by the court with
damages awarded based on the 'cost of cure' technique. This included higher
labour, material, and administrative expenses that the business was forced to
pay due to the project's adjustments and longer timetable.
Second, Maula Bux was
awarded damages by the court on the 'loss of profit' technique to make up for
the loss of projected earnings that the company would have rightfully made if
the contract had been carried out without any modifications or delays. The court
took into account the profit margin Maula Bux would have received if the project
had been finished as planned.
The Hon'ble Supreme Court formulated the
following: It is well settled that in every case of breach of contract the
person who suffers breach of contract is not bound to establish that he has
suffered loss or damage before he can claim a decree for breach and the court is
fully competent to award reasonable compensation or damage in case of breach
even if he has not suffered any actual loss in the consequence of the breach of
contract. But the expression "whether or not actual damage or loss is proved to
have been caused there by" is intended to cover different classes of contracts
which come before the courts. In case of breach of some contracts it may be
impossible for the court to assess compensation arising from breach, while in
other cases compensation can be calculated in accordance with established Rules.
Where the court is unable to assess the compensation, the sum named by the
parties if it be regarded as a genuine pre-estimate may be taken into
consideration as the measure of reasonable compensation, but not if the sum
named is in the nature of a penalty. Where loss in terms of money can be
determined, the party claiming compensation must prove the loss suffered by him. [xxi]
Damage allows either party in a building contract to seek restitution according
to sections 73 and 74 of the Act. Another key underlying principle for ensuring
fair treatment of contracting parties is contained in the provision of the
Indian Contract Act, specifically Section 73 of the Act. Section 73 of the Act
is a very important provision that sheds light on the justice in the contract
which has occurred between two parties. Scholars study the intricate details and
stringent requirements of Section 73 of contract law, which addresses damages
for injury or loss resulting from contract breach. This provision effectively
embodies the core concept of contractual fairness; it seeks to reimburse the
injured party for losses sustained as a result of the other party's error or
failure to execute under the terms of the contract.
In order to understand the complexities of Section 73, academics carefully
examine its requirements and component parts. These include demonstrating the
existence of a contract that is legally enforceable, demonstrating that a breach
took place, and demonstrating that the loss or injury sustained was directly
brought about by the infraction. Scholars also look at the maximum damages
allowed by this provision, which often aims to restore the injured party to the
identical circumstances that were in the absence of the breach rather than
giving them windfall profits. Academicians examine case law interpretations to
gain a deeper understanding of the nuances of Section 73.
These interpretations
offer important insights into the evolution and application of the Act.
Academics pinpoint new developments in the interpretation of the law, clarify
the legal justification for judgments concerning damages for breach of contract,
and specify the bounds of the discretion that courts have when making awards.
This enhances our understanding of the principles governing compensation for
breach of contract and improves the effectiveness of legal frameworks in
protecting the rights and interests of contracting parties. In the realm of
contract law, Section 74 holds significance for its delineation between
penalties and liquidated damages, particularly pertinent in contexts such as
construction contracts. The subtle difference between these two ideas is
essential to academic debate.
The penalties, therefore, are sanctions that are
applied to discourage the non-performance and, on the other hand, liquidated
damages are the pre-estimated amounts of money for losses or the damages that
may be incurred in the event of a breach of the contract. Comprehending this
contradiction is crucial for academics debating the implementation of Section
74, particularly in the intricate field of construction contracts where
significant risks are involved.
In addition, they examine whether the sums specified are appropriate given the
projected loss or damage, taking into account variables including the project's
nature, industry norms, and the parties' negotiating leverage. Research academic
scholars contribute to the development of strong legal frameworks that strike a
balance between fostering contractual certainty and protecting against unjust
penalties, thereby improving the efficiency and fairness of contractual
relationships in the construction industry. They do this by navigating the
complexities of Section 74 within the specific context of construction
contracts.
Courts take into account a number of variables to distinguish: Is the agreed
upon amount accurately indicative of the possible loss, or is it an outrageous
amount intended to discourage violations? Does the provision take into
consideration the seriousness of certain contract violations? Section 74 is
especially pertinent to construction contracts since delays and unanticipated
events are frequent occurrences in these contracts. Claiming compensation for
minor delays may be made easier and more predictable administratively with the
use of liquidated damages provisions.
However, Courts will carefully review these provisions to make that the harm
caused by a particular delay is fairly estimated, taking into account things
like the cost of equipment and idle labour. Through the implementation of
suitable liquidated damages provisions, Section 74 promotes equilibrium between
incentivizing punctual performance and averting undue financial strain on the
party in violation.
Conclusion
The study of the Act's sections 73 and 74 reveals a framework for handling
damages for contract violations in the construction industry. While Section 74
permits predetermined reimbursement through liquidated damages, Section 73
guarantees justice for the non-breaching party. For those involved in the Indian
construction sector, however, understanding the nuances of these sections has
important consequences.
Owners need to put careful contract writing first. It is essential to include
explicit, enforceable liquidated damages clauses that account for possible
losses. Excessive or ambiguous phrases run the possibility of being upheld as
sanctions, which would impede the healing process. On the other hand,
contractors must to carefully go over these conditions in order to prevent fines
that appear as liquidated damages. Gaining a better comprehension of Sections 73
and 74 enables individuals to bargain for more equitable conditions in
contracts.
Strategic actions can enhance the legal system in the future. Investigating the
use of industry-standard delay formulae in model contracts is one interesting
direction. By doing this, the claims process would be streamlined, disagreements
would be reduced, and liquidated damages would be assessed with better
consistency and predictability. It's also critical to support instructional
programs on Sections 73 and 74 for all parties involved. A culture of proactive
risk management might be fostered by a better-informed contractual environment,
reducing delays and violations. Furthermore, a more sophisticated interpretation
of foreseeability under Section 73 will strengthen the legal framework in light
of the dynamic character of building projects.
Foreseeability of damages in the
context of unanticipated situations would be evaluated by courts according to
clear rules, which would give both owners and contractors more certainty. In
order to give stakeholders more clarity and predictability in contract
negotiations and enforcement, legislative and regulatory changes should, first
and foremost, clearly define the distinction between penalties and liquidated
damages.
To encourage uniformity and coherence in legal interpretations, this
may entail creating model clauses or publishing judicial guidelines. Second,
encouraging fairness and openness in contract discussions can reduce the
likelihood of disagreements and legal action, encouraging cooperation and
confidence between the involved parties. To achieve this, it might be necessary
to push for transparent communication, the sharing of pertinent data, and fair
negotiations that take into account the interests of all parties involved.
In conclusion, the development of a legislative framework that maintains equity
for all stakeholders is essential to the health and productivity of the Indian
construction industry. Stakeholders may traverse the complexity of damages with
more confidence if the aforementioned ideas are put into practice. This will
ultimately lead to a more streamlined and predictable construction environment,
which will support India's infrastructure development.
End Notes:
- Indian Contract Act, 1872, No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 73, No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 74, No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 2, cl. (e), No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 2, cl. (a), No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 3, No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 2, cl. (d), No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 10, No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 11, No. 09, Acts of Parliament, 1872 (India).
- Indian Contract Act, 1872, § 37, No. 09, Acts of Parliament, 1872 (India).
- Annapurna Mishra, The Law of Damages Under Indian Contract Act, 1872, Abbasi & Associates Law Firm (May 22, 2024, 7:29 P.M.), https://abbasilegal.com/the-law-of-damages-under-indian-contract-act-1872/
- B.V.R Sarma, Adjudication of Claim for Damages under Sections 73, 74 and 75 of Indian Contract Act, 1872, Manupatra (May 24, 2024, 6:12 P.M.), http://docs.manupatra.in/newsline/articles/Upload/30C28D5D-262B-4A4A-AE17-C4D86F92BCE0.pdf
- Deepika M., Damages under the Indian Contract Act 1872, VidhiNama (May 29, 2024, 4:14 P.M.), https://vidhinama.com/damages-under-the-indian-contract-act-1872/
- Haryana Telecom Ltd. v. Union of India, AIR 2006 SCC Del 575.
- Accounting Standard (AS) 7 Construction Contracts, (May 31, 2024, 7:34 P.M.), https://www.mca.gov.in/Ministry/notification/pdf/AS_7.pdf
- Id.
- The Specific Relief Act, 1963, No. 47, Acts of Parliament 1963 (India).
- Kailash Nath Associates v. Delhi Development Authority, AIR 2015 SCW 759.
- Universal Pvt. Ltd. v. B. E. Bilimoria & Co. Ltd., AIR 2016 (5) Mah L.J. 229.
- Maula Bux v. Union of India, AIR 1970 SC 1955.
- Id.
Please Drop Your Comments