Brief facts of the case:
The parties in CVG v CVH were in a franchise business, with the Respondent being
the Petitioner's franchisee in Singapore, Malaysia, Taiwan, and the Philippines.
The authoritative connections among the parties were administered by four
different Franchise Agreements ("Agreements"). Disputes arose regarding some
alleged breaches of the Agreements following a management change at the
Claimant's company as a result of a successful bankruptcy protection action
filed by the Claimant under Chapter 11 of the United States Bankruptcy Code.
The Defendant disassociated themselves from the Claimant's corporate group after
terminating the Agreements on the grounds of anticipatory repudiation and
material breach. The Defendant considered the Claimant's refusal to grant access
to its Singapore-based corporate group to be acceptance of their agreements'
termination.
The Claimant then filed an arbitration with the International Centre of Dispute
Resolution (ICDR). The arbitration was situated in the US territory of
Pennsylvania and Pennsylvanian regulation administered the procedures.
Additionally, the Claimant sought emergency measures. The Claimant argued in
favor of applying the Agreements' agreed-upon post-termination provisions during
the emergency measures hearing. The Claimant made a significant argument in its
post-hearing submissions that it did not yet consider the Agreements to have
been terminated.
Because the Claimant did not consider the Agreements to have ended, the
emergency arbitrator made an award that maintained the status quo of the parties
in place prior to the Agreement's termination. The Respondent objected to the
Claimant's application to enforce the award in the Singapore High Court. The
decision was made in response to this case before the High Court.[1]
Case Analysis: The High Court took a purposive translation of the
legislative plan and plan of the International Arbitration Act and found that
the meaning of 'arbitral tribunal' in Section 2(1) of the Act would stretch out
to Section 3 of the Act in Section 27(1).
The High Court, nonetheless, rushed to raise objection with the enforcement of
emergency arbitration on the ground that it disregarded principle of natural
justice since the Respondent could not put forth its viewpoint in that frame of
mind of specific submissions made by the Petitioner in its post-hearing
submissions. During the emergency arbitration hearing, the arbitral court had
enquired about the elective submissions of the Petitioner, in the occasion, the
mentioned emergency measure was not conceded. In addition, the tribunal had
included this concern on the list of issues that the parties were required to
address in their post-hearing arguments.
The High Court decided that the award was made based on the Claimant's
alternative submission at the post-hearing submission stage, despite the fact
that it was within the parties' and their submissions' contemplation that the
decision on the matter would be with respect to the new case of the Claimant
regarding its treatment of the status of the Agreement, satisfying the
requirements under Section 31(2)(c) of the Act. The High Court thus decided that
the Claimant's submission altogether strayed from its prior position during the
hearing stage.
End-Notes:
- CVG v. CVH [2022] SGHC 249.
Please Drop Your Comments