Schiller And Ors. V. Sooltan Chand And Ors.
Facts Of The Case
- The appeal stems from a ruling rendered in the Original Jurisdiction of the High Court by Mr. Justice Pontifix, wherein the plaintiffs' claim was decreed with costs.
- The lawsuit pits the plaintiffs and the defendants against one another over damages caused by the unlawful rescinding of a contract. A sold note dated February 23, 1877, delineated the conditions of the agreement concerning the purchase of 200 tonnes of newly harvested small grain linseed from the upcountry.
- The linseed was to be delivered to Howrah Railway Station between April and May 1877, as per the terms of the contract. It was the responsibility of the plaintiffs to deliver the linseed sacks by March 20, 1877. The terms of payment stipulated cash on delivery.
- In accordance with their contractual duty, the plaintiffs dispatched the linseed sacks prior to the designated deadline. From 1 April to 8 May 1877, the perpetrators executed partial shipments of the linseed.
- The plaintiffs remitted Rs. 1,000 to the defendants on May 5, 1877. However, when the defendants requested the balance, they declined or failed to do so, invoking damages and refraction claims that surpassed 4 percent.
- On May 12, 1877, in response to the plaintiffs' nonpayment of the complete sum, the defendants terminated the agreement and ceased all subsequent shipments. The defendants contend that rescinding the contract under Section 39 of the Contract Act is warranted due to the plaintiffs' non-payment upon delivery. Sections 51 and 55 are also referenced in support of their position.
- The plaintiffs argue that they did not completely impede or refuse to perform their obligation as promised. They contend that Section 55 governs the situation and that Section 39 is inapplicable to their case.
- In accordance with the plaintiffs' position, Mr. Justice Pontifix ruled that the defendants lacked justification for rescinding the contract. In determining the plaintiffs' compensation, he assessed the discrepancy between the contract price and the subsequent market price of linseed.
- The defendants filed an appeal of the decision, contending that their rescinding of the contract was warranted in light of the plaintiffs' non-payment upon delivery and not a breach of the agreement.
Case Comment:
(1878) ILR 4 Cal 252
Decided On: 22.07.1878
In The High Court Of Calcutta
Hon'ble Judge: Richard Garth (Chief Justice) and William Markby (Justice)
Appellant: Schiller and Ors.
Respondent: Sooltan Chand and Ors.
Issues of the Case
- An evaluation of whether the defendants' assertion that sections 51 and 39 of the Contract Act constitute a sound defence in the lawsuit.
- Determine whether or not Section 39 of the Contract Act is relevant to the current situation.
- Determine whether the plaintiffs are entitled to compensation in the form of damages equal to the discrepancy between the contract price and the market price of linseed.
- Whether the defendants' refusal to fulfil the contract is justified on the basis of the plaintiffs' nonpayment upon delivery?
Arguments
Appellants' Arguments:
- The plaintiffs contend that their complete non-performance of the promise constituted no refusal. They expressed their readiness to remit the outstanding balance once their disputes regarding damage and refraction were resolved.
- According to the plaintiffs, Section 39 of the Contract Act is inapplicable to their situation. They argue that the section applies to circumstances in which a party completely fails to fulfil their contractual obligations or is incapacitated from doing so, which contradicts their conduct.
- They contend that the situation is governed by Section 55 of the Contract Act. They assert that the parties did not intend for payment to be made at the exact moment of delivery to be a condition of the agreement.
- Perpetrators argue that they are entitled to compensation for damages resulting from the improper rescinding of the contract. They are pursuing reparation for the discrepancy that arose between the contract price and the succeeding market price at which they acquired linseed.
Defendants' Arguments:
- The defendants contend that the plaintiffs breached their entire obligation by declining payment upon delivery. They contend that Section 39 permits rescission for any breach of performance of the contract.
- The defendants argue that their rescinding of the agreement was warranted on account of the plaintiffs' non-payment upon delivery. They contend that their position is supported by Sections 51 and 55.
- The defendants contend that the plaintiffs are not entitled to maintain a claim for damages because they breached the contract by failing to be prepared and willing to pay upon delivery.
- The defendants contest the assessment of damages in their appeal, arguing that it should be computed using the market rate on May 12 instead of May 15.
JUDGEMENT
Chief Justice Richard Garth:
By appealing the verdict, the defendants argued that the plaintiffs' refusal to
pay for the items upon delivery was sufficient grounds for terminating the
contract in accordance with Sections 39[6] and 51[7] of the Indian Contract Act
of 1872. Their appeal was successful.
Section 396 is applicable in situations when a party either completely refuses
to meet their obligations under the contract or is unable to fulfil their
obligations due to a disability.
In the case of Freeth v. Burr[8], which is a good example of Section 39, the
defendants were not justified in refusing to complete the contract. This is
because the plaintiffs had not refused to pay for the products; rather, they had
merely delayed payment.
There is a possibility that the illustration in Section 39, which speaks of a
singer's unwillingness to perform at a theatre, could be misunderstood;
nonetheless, this particular instance does not fit the description.
Due to the fact that the defendants did not demand on stringent performance and
rapid payment upon delivery, Section 517, which is concerned with reciprocal
commitments, does not apply.
The defendants did not insist on quick payment on delivery, as indicated by
previous deliveries that were made without demanding payment. This is despite
the fact that Section 55[9] may have given the impression that time was of the
essence under the contract.
The appeal is upheld, and fees will be incurred.
William Markby, J.:
A mercantile arrangement of this nature does not fall under the purview of
Section 39.
Only in the event that the defendants had insisted on tight performance and
timely payment upon delivery would Section 517 have been applicable; however,
they did not do so.
Despite the fact that Section 558 may give the impression that time was of the
essence, the defendants did not insist on receipt of money immediately upon
delivery.
Due to the fact that the plaintiffs did not pay on delivery in line with the
terms of the contract, the defendants are unable to provide a justification for
their reluctance to continue with the contract under the current circumstances.
The appeal is upheld, and fees will be incurred.
Ratio Decidendi:
Interpretation of Section 39 The Indian Contract Act applies Section 39 in
situations when a party either completely refuses to meet their obligations
under the contract or is unable to fulfil their obligations under the contract.
Examples of precedents that help interpret Section 39 include Freeth v. Burr,
which demonstrates that a refusal to pay in a timely way does not imply a
refusal to complete the contract in its entirety.
If the promisor does not demand on tight performance and rapid payment upon
delivery, then Section 51, which is about reciprocal promises, does not apply.
This is because Section 51 is not applicable.
In spite of the fact that Section 55 implies that time may be of the essence in
contracts, it is not relevant in situations where the parties did not insist for
quick payment upon delivery.
The activities of the defendants, which include providing deliveries without
demanding immediate payment and accepting lump-sum payments on account, give the
impression that they did not take into consideration the fact that time was of
the importance before making their decisions.
As a result, the defendants are unable to provide a valid reason for terminating
the contract on the grounds that the plaintiffs did not precisely comply to the
payment obligations.
Relevant Laws:
-
Section 2(h) of the Indian Contract Act, 1872: According to Section 2(h), a "contract" is defined as an agreement that is legally enforceable.
-
Section 39 of the Indian Contract Act of 1872: Addresses the issue of anticipatory breach of contract. In the case of Schiller and Others v. Sooltan Chand and Others, the defendants made a settlement with the plaintiffs in which they agreed to furnish 200 tonnes of linseed to them at a defined price.
-
Section 51 of the Indian Contract Act, 1872: Deals with the performance of reciprocal promises, a crucial aspect of the case.
-
Section 73 of the Indian Contract Act, 1872: The remedy for violation of contract is outlined in Section 73. As a result of the breach of contract, it allows for the reimbursement of any loss or harm that may have occurred.
Case Comment
Schiller and Ors. v. Sooltan Chand and Ors is a case that goes back to the 19th
century and is considered to be a historical Indian contract law case. In this
particular case, Schiller was found to have violated the terms of the contract
by failing to deliver the 250 tonnes of linseed that had been agreed upon to
Sooltan Chand. It is important because it exemplifies the application of the
theory of anticipatory breach, which was firmly established by the English
decision of
Hochster v. De la Tour[12] in 1853. This case is notable because it
depicts the application of the principle.
The English common law had a significant impact on the Indian judiciary's
understanding of anticipatory breach. The Indian Contract Act of 1872, which was
modelled after the English Act of 1855, was the legislation that integrated the
theory of anticipatory breach. As an illustration of how this principle might be
applied in the Indian setting, the case of
Sooltan Chand v. Schiller is provided
as an example.
Due to the fact that the plaintiff's repeated attempts to settle their
cross-claims did not demonstrate a purpose to breach the contract, the defendant
was not held accountable for anticipatory breach. This decision was particularly
significant because it underscores the relevance of the "intention" element in
contract law.
Despite the fact that the case is not directly accessible through the search
results that have been supplied, the information that has been provided suggests
that it is a well-known and influential case in the history of Indian contract
law.
Conclusion:
The High Court heard
Schiller and Ors. vs. Sooltan Chand and Ors., an appeal
against a verdict granting the plaintiffs' contract rescission damages. The
arrangement required selling 200 tonnes of linseed for delivery at Howrah
Railway Station in April and May 1877. The contract required cash payment on
delivery, and the plaintiffs delivered the required linseed sacks before the
deadline. However, when the defendants supplied partial quantities of linseed,
the plaintiffs refused to pay the full amount owed due to quality difficulties.
The defendants invoked Sections 39 and 51 of the Indian Contract Act of 1872 to
rescind the contract since the plaintiffs allegedly failed to pay for the items
on delivery. They claimed Section 39 enabled them to cancel the contract because
the plaintiffs had not paid in full upon delivery. The court disagreed, stating
that Section 39 applied to parties who explicitly refused to meet their contract
obligations. It stated that the plaintiffs' unwillingness to pay in full was
because to valid worries about the linseed's quality, not a refusal to complete
the contract.
Section 51, which governs simultaneous reciprocal promises, was also examined by
the court. The defendants' promise to supply linseed and the plaintiffs' promise
to pay were reciprocal. The defendants' omission to demand prompt payment upon
delivery weakened their claim that time was of the essence in the contract.
The court also reviewed Section 55, which covers contract performance time. It
rejected the claim that rapid payment upon delivery was necessary to the
contract because the defendants had made multiple deliveries without demanding
payment. Inconsistency in the defendants' actions weakened their contention that
failing to pay on delivery justified contract rescindment.
The court stressed that the law enforces the parties' contract objectives in its
judgement. The plaintiffs' actions were consistent with their plan to pay for
the linseed upon satisfactory delivery, and their failure to pay in full was a
fair response to quality concerns.
The court rejected the defendants' appeal and confirmed the lower court's
verdict, awarding the plaintiffs' claim with costs. The judgement stressed the
need of interpreting contract law fairly and equitably. It reminded us to
evaluate contractual duties based on the facts of each situation, taking into
account the parties' intentions and the practicalities of the contract.
Bibliography
Statutes:
- Indian Contract Act, 1872, § 39, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 2(h), Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 51, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 55, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 73, Acts of the Parliament, 1872 (India)
Case References
- Schiller and Ors. v. Sooltan Chand and Ors. (1878) ILR 4 Cal 25
- Hochster v. De la Tour, 1853
- Freeth v. Burr, (1874) LR9 CP 208
End Notes
- Indian Contract Act, 1872, § 39, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 51, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 39, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 55, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 51, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 39, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 51, Acts of the Parliament, 1872 (India)
- Freeth v. Burr, (1874) LR9 CP 208
- Indian Contract Act, 1872, § 55, Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 2(h), Acts of the Parliament, 1872 (India)
- Indian Contract Act, 1872, § 73, Acts of the Parliament, 1872 (India)
- Hochster v. De la Tour, 1853
Please Drop Your Comments