The world is undergoing a global crisis and outbreak of COVID- 19 which is
wreaking havoc globally and turns out to be an unprecedented event in world
history. The World Health Organisation (WHO) on March 11, 2020, declared the
COVID-19 as a pandemic stating that
Pandemic is not a word to use lightly or
carelessly. It is a word that, if misused, can cause unreasonable fear, or
unjustified acceptance that the fight is over, leading to unnecessary suffering
and death.[3]
As India has officially announced a
complete national lockdown
on March 25th, 2020, to seek measures to control the spread of an ongoing global
pandemic, with nearly 400,000 people tested positive for the virus worldwide,
and around 17,000 have died worldwide.[4]
COVID – 19 can be seen as a killer blow not only on human health but also on the
economic health of the nation causing the economy to face an unprecedented
market crash. With the advent of events going on the closing down of market and
breakdown of the supply chain, creates questions on the performance of contracts
of varied nature leading to delays, obtrusion and even suspension of the
contracts. In the light of rapid spread of the outbreak and the response as
undertaken by the government, this article covers the enforceability of
the ‘Force Majeure’ clause in commercial contract and also discusses the
approach of the Indian Courts towards the same going by the law as laid down in
The Indian Contract Act, 1872.
The Concept of Force Majeure:
Force Majeure is the French term that can be translated as
irresistible
compulsion or coercion.[5]
Force Majeure is a legal term in French law and
was derived from the code of Napoleon and applied for the first time in the
Civil Code of France.
Force Majeure occurs when the law recognizes that without default of either
party, a contractual obligation has become incapable of being performed because
the circumstances in which the performance is called for, has rendered the
performance impossible. According to Black’s Law Dictionary, Force Majeure is
defined as An event or effect that can be neither anticipated nor
controlled.[6]
In other words, Force Majeure refers to events outside the control of parties
and which prevent one or the both of the parties from performing their
contractual obligations.[7]
The essential ingredients of the Force Majeure include:
- the event must be beyond the reasonable control of the affected party;
- the affected party’s ability to perform its obligations under the
contract must have been prevented, impeded or hindered by the event; and
- the affected party must have taken all reasonable steps to seek to avoid
or mitigate the event or its consequences.
It is also essential to observe that the presence of the Force Majeure clause
does not entirely excuse a partys performance, but only suspends it for the
duration of the event which essentially makes the performance of the contract
impossible. However, if the Force Majeure clause provides that where Force
Majeure continues for more than a stipulated period then either party may at its
own option terminate the contract without any financial repercussion on either
side.
The presence of the Force Majeure clause is essential in a contract as the
Indian law does not provide implied defence for the non performance. It would
not be out of place to state that in the case of non-performance of the
contractual obligation by the party, the language of the clause will become the
key factor in granting any kind of protection in the event of the outbreak of
COVID-19.
Key Aspects In Claiming A Relief Under Force Majeure Clause In India
It is needless to mention that the Indian Government is considering the outbreak
of COVID-19 as Force Majeure. The Ministry of Finance of India has issued a
clarification through an office memorandum as below:
A doubt has arisen if the disruption of the supply chains due to the spread of
coronavirus in China or any other country will be covered in the Force Majeure
Clause (FMC). In this regard, it is clarified that it should be considered as a
case of natural calamity and FMC may be invoked, wherever considered
appropriate, following the due procedure as above.[8]
As COVID-19 pandemic has made it more difficult for parties to perform their
contractual obligations. There are two possible situations, which may suggest
that a Force Majeure clause covers a pandemic:
- if the contractual definition of a Force Majeure event expressly includes
a pandemic.
- if the Force Majeure clause covers extraordinary events or circumstances
beyond the reasonable control of the parties. Such general, catch-all
wording may be invoked if it is determined that the factual circumstances
caused by the pandemic are beyond the reasonable control of the affected
party.[9]
Further, the relief from the Force Majeure event can be attained by providing
certificates issued by the Government agencies to the affected parties yet they
are not determinative. The WHOs categorization of the outbreak as a pandemic
may be of significant persuasive value in cases where the Force Majeure
provision contains appropriate language regarding the events of Force Majeure.
A contract could also place a duty on performing party to mitigate the effect of
its non-performance on the other party. This duty could be contained in a best
endeavors clause. In order to successfully invoke a Force Majeure clause to
excuse liability for non-performance, a party under a contractual duty to
mitigate or make best endeavors will be required to demonstrate the efforts it
undertook to mitigate the impact of its non-performance.[10]
The burden of proof is on the non-performing party to put forth instances and
prove the validity of its claim for Force Majeure relief. It has to adduce
evidence that an event of Force Majeure occurred, which was beyond its
reasonable control and which prevented or delayed its performance of the
affected obligations and thus the party has not breached the contract and it is
entitled to the relief of Force Majeure.
The Indian Jurisprudence Covering Force Majeure In Commercial Contracts
The Indian Contract Act, 1872, does not expressly cover
Force Majeure,
however, there are two sections that are relevant to the concept of Force Majeure:
- Firstly, section 32 of the Act,[11] covers Contingent Contracts under
which the performance of a particular contract is contingent on happening or
non-happening of a particular event.
- Secondly, the practical utility of Force Majeure contrasts with the rigid common law doctrine of frustration, although
they are similar in the sense that they both deal with occurrences beyond the
control of parties to an agreement laid down as sec 56 of the Act.[12]
Under the doctrine of frustration, where after the execution of a contract, the
emergence of supervening circumstances beyond the control of the parties renders
further performance of the contract impossible or radically different from what
had been contemplated in the contract, the contract will be terminated and the
parties will be discharged from the requirement of further performance.
The Supreme Court of India has reiterated the Doctrine of Frustration,
Impossibility and Force Majeure in a plethora of judgments ranging from:
In
Satyabrata Ghose v. Mugneeram Bangur and Co. and Anr.,[13] Mukherjee J.,
illustrated the doctrine of frustration and also dealt with Section 56 at length
as under:
The first paragraph of the section lays down the law in the same way as in
England. It speaks of something which is impossible inherently or by its very
nature, and no one can obviously be directed to perform such an act.
The second
paragraph enunciates the law relating to the discharge of contract because of
supervening impossibility or illegality of the act agreed to be done. The
wording of this paragraph is quite general, and though the illustrations
attached to it are not at all happy, they cannot derogate from the general words
used in the enactment. This much is clear that the word impossible has not
been used here in the sense of physical or literal impossibility.
The performance of an act may not be impossible but it may be impracticable and
useless from the point of view of the object and purpose which the parties had
in view; and if an untoward event or change of circumstances totally upsets the
very foundation upon which the parties rested their bargain, it can very well be
said that the promisor found it impossible to do the act which he promised to
do.
The Supreme Court in
Dhanrajamal Gobindram vs Shamji Kalidas And Co., dealing
with Force Majeure held that McCardie J. in
Lebeaupin v. Crispin,[14] has given
an account of what is meant by Force Majeure with reference to its history.
The expression
Force Majeure is not a mere French version of the Latin
expression vis major. It is undoubtedly a term of wider import. Difficulties
have arisen in the past as to what could legitimately be included in
Force
Majeure. Judges have agreed that strikes, breakdown of machinery, which, though
normally not included in vis major are included in
Force Majeure.
An
analysis of rulings on the subject into which it is not necessary in this case
to go shows that where reference is made to
Force Majeure, the intention is to
save the performing party from the consequences of anything over which he has no
control. This is the widest meaning that can be given to
Force Majeure,
and even if this be the meaning, it is obvious that the condition about
Force Majeure in the agreement was not vague. The use of the word usual makes all
the difference, and the meaning of the condition may be made certain by evidence
about a Force Majeure clause, which was in contemplation of parties.[15]
More recently, the Hon’ble Supreme Court in
Energy Watchdog vs Central
Electricity Regulatory,[16] observed that:
In so far as a Force Majeure event occurs de hors the contract, it is dealt with
by a rule of positive law under Section 56 of the Contract. The performance of
an act may not be impossible but it may be impracticable and useless from the
point of view.
Though holding a higher degree of standard to decide the same, the Indian Courts
have been more inclined towards the frustration of contracts.
The most important
factor in demanding relief by the parties for the non-performance of contract
amid COVID-19 will be the difficulty in the circumstances falling outside the
reasonable control of the parties which led to the frustration of contract. The
reasons mentioning the cost of performance bringing into account the expenses to
perform the contract which made the performance inconvenient to the party would
not fall under the ambit of Force Majeure.
The basis test which will be necessary for the parties to pass for the non
performance of the contract would lie around establishing that whether it was
the hardship or the impossibility of the circumstances which led to non
performance of contract and the latter would be at a better stance to get a
positive nod from the Courts.
Conclusion
The doctrine of Force Majeure has a limited and restrictive application and
owing to which the parties are at the liberty to find a way round to doctrine of
frustration and can claim frustration of contract in non- performance of the
contract. Although the overall enforceability of the clause of Force Majeure to
be invoked will depend on the individual nature of commercial contract, the
grave character of the pandemic will also help the parties to receive a generous
attitude from the Court.
After all, the government pursuing a complete lockdown
of a country as big as India surely counts. It would be reasonable for the
commercial entities to be ready with a contingency plan while considering the
alternative ways for the performance of the obligations in case the situation
gets worse as India is still witnessing the early phases of the pandemic. It
would be just that a fact-specific analysis of the commercial entity’s
contractual relationship should be done by the executives, as a precautionary
measure to reduce the aftermaths of COVID-19.
Looking into the present scenario, it seems inevitable that India as an economy
is going to witness a slowdown and therefore, the parties and commercial
entities should make the prior arrangement to endure the lowest financial loss
by keeping a detailed review of their supply chain, making the essential
correspondences and communications in case the dispute arise, amongst others.
End-Notes:
- x
- Coronavirus disease (COVID-19) Pandemic, World Health Organisation (Mar
28, 16:30),
.
- Coronavirus: India enters total lockdown after spike in cases, BBC
News Services, (Mar 28, 16:30)
- Oxford dictionary of Law, 9thed. (2003)
- Black’s Law Dictionary, 11th ed.,(2019)
- P. Ramanatha Aiyar, Advanced Law Lexicon, 5th ed, p- 2077.
- Office Memorandum No.F. 18/4/2020-PPD titled ‘Force Majeure Clause’,
issued by Department of Expenditure, Procurement Policy Division, Ministry
of Finance, Government of India
- Coronavirus, Force Majeure and impact on Commercial Contracts,
BloombergQuint, (Mar 28, 16:30)
- Impact Of Covid-2019 On Contracts: Indian Law Essentials, (Mar 28, 16:30
PM),
- Section 32 of The Indian Contract Act, 1872.
- Section 56 of The Indian Contract Act, 1872.
- AIR 1954 SC 44.
- (1920) 2 K.B. 714
- AIR 1961 SC 1285.
- (2017) 14 SCC 80
Written By:
- Aishwarya Anand - Senior Associate, Singhvi & Co., Advocates and
Legal Consultants, Jodhpur, Rajasthan. His email ID is [email protected] and
he can be reached at +91 9782954559.
- Kritika Singh - 3rd Year Student, Maharastra National Law
University, Aurangabad. Her Email ID is [email protected] and she
can be reached at +91 9571543039.
Please Drop Your Comments