There was an award on expropriation given by the Tribunal. It found that
Italy had expropriated Rockhopper's investment without compensation, thus
deeming it unnecessary to decide the other claims (para. 200).[1] It then went
on to find that, under Italian law, the approval of Rockhopper's EIA in August
2015 bestowed on Rockhopper a right to be granted the final exploitation permit,
which had been "wiped out" by the rejection of the application in January 2016 (para.
169).[2]
Italy timidly tried to argue that no expropriation could be carried out
in relation to an activity that had not started yet – an argument with which the
Tribunal was unimpressed, confirming that the "wiping out" of the entitlement to
the concession was, in itself, expropriation (paras. 194-196).
How was the principle of Environmental legitimacy dealt with?
There was a strong uprise against offshore production in Ombrina Mare related to
environmental factors, however, the outcome of this case passes no judgement
whatsoever on the legitimacy or validity of those views. The case only addresses
the legal issue at hand. The Tribunal only examined the legislative history and
held that environmental factors were secondary to this case. More importance was
given to the political uprisings in the state and the conflict between the
Parliament and the local community. The Tribunal severed the connection between
environmental degradation and Italy's conduct.
When Italy banned offshore production in late 2015, the Tribunal held this act
to be Italy's sovereign choice and not to criticize it either from a political
or environmental standpoint. Then, Italy issued a law banning all offshore
production activities within 12 nm of the coastline as it degraded the marine
environment and demanded an Environment Impact Assessment and also the opinion
of the local authorities located within 12 nm of the marine and coastal areas
affected by the activities. On 6 March 2015, the Respondent's Ministry of the
Environment and the Protection of Land and Sea issued a detailed and lengthy
document (C-114) approving "Rockhopper's EIA application.
This called for an
enormous negative reaction from the Abruzzo Region and the local communities.
The Conference of Services was called for to acquire the missing opinions. This
was a big blow to the claimants. However, the Tribunal held that the claimants
had duly satisfied all the requirements for "environmental compatibility."
What were the key claims made under ISDS and ECT? (identified below are any
three)
The claims under ISDS and ECT were:
- The Claimants advance their case on liability on three separate strands, namely, impairment, fair & equitable treatment, and unlawful expropriation.
- The ECT provides, in Article 13(1), a standard of compensation for lawful expropriations. However, that standard is not taken to apply, as in this case, to instances of unlawful expropriation. Therefore, the standard of compensation is to be drawn from customary international law.
- The Claimants review three potential valuation systems:
- Discounted Cash Flow (DCF)
- Market Transactions
- A sunk-costs approach
The Claimants favour the DCF model for compensation in this arbitration. The Respondent does not believe the DCF model is appropriate to value Ombrina Mare and instead favours a Market Transaction based approach.
What are the limitations of this award?
In this case, the Tribunal has not been asked to direct that such production
should go ahead. The sole and key matter for the Tribunal to decide is whether
or not the Claimants are entitled to compensation pursuant to international law
(as a matter of the ECT) for certain actions of Italy. Further, the Tribunal is
also at pains to say that any such compensation could only arise, under
international law, if the sovereign promises and actions of Italy triggered such
rights on the part of the Claimants.
The award so passed was ignorant of the environmental issues of Italy's actions.
The Tribunal dismissed the police powers defence by stating that Rockhopper's
application was rejected due to political concerns and not because of
environmental factors. But it should have been kept in mind that when a
government bans any activity due to reasons of the local uprising, that
particular reason becomes the subject- matter of the case ie environmental
concerns. The case fails to reach out to the audience as to how climate policy
is dealt with in ISDS.
The decision has quickly become symbolic of the incompatibility of the ECT with
efforts at tackling the climate crisis (Italy had already withdrawn from the ECT
in 2015, but Rockhopper benefitted from the treaty's sunset clause, which
extends its application to pre-withdrawal investments for a further 20
years).[1] The Tribunal ignored the fundamental question ie Whether a right to
expropriation must possess a proprietary nature? This case implied that
expropriation is possible in both contractual rights and preliminary rights to
the contract.
The next limitation of the award was the choice of appropriation of valuation
method to determine the investor's loss. The Tribunal went with the DCF
valuation instead of sunk cost approach and the market-based approach only
because DCF it widely used in financial practice than the latter approaches.
Regrettably, the Tribunal treated valuation as a purely financial issue, as ISDS
Tribunals, unfortunately, tend to do, rather than one deeply entangled with the
environmental preoccupations that lay behind the offshore ban.
How has the domestic law influenced the IIA of the host country?
Yes, domestic law did influence the International Investment Agreement. Firstly,
the laws that were enacted by Italy that no offshore production shall be allowed
within 5 nm and then amending it to 12 nm, affected the investment agreement as
these conditions were not provided before by Italy. Bringing such laws when the
agreement is enforced influenced the whole case revolving around these municipal
laws. Only because these municipal laws affected the investment agreement, there
was this case in the first place.
Secondly, the domestic law required the claimant to conduct an Environment
Impact Assessment which was not provided in the Investment Agreement. But the
municipal government demanded the same. It became a vital part of deciding
whether to proceed with the subject matter. The importance of the agreement here
became a subsidiary of the Environment Impact Assessment results. Thirdly, the
valuation method that was adopted by the Tribunal ie the DCF method was nowhere
mentioned in the investment agreement. It was the decision of the Tribunal
influenced by the market popularity and finance practice.
End Notes:
- Toni Marzal, 'Polluter Doesn't Pay: The Rockhopper V. Italy Award' (EJIL
19 January 2023) <https://www.ejiltalk.org/polluter-doesnt-pay-the-rockhopper-v-italy-award/>
accessed on 18 May 2023.
- Paolo Mazzotti, Rockhopper V. Italy and the Tension between ISDS and
Climate Policy (International Law and International Legal Thought 21
December 2021) <https://voelkerrechtsblog.org/de/rockhopper-v-italy-and-the-tension-between-isds-and-climate-policy/>
accessed on 18 May 2023.
- Ibid.
Please Drop Your Comments