India recognized resolving disputes by way of mediation and reconciliation
from Vedic era. However, codified law on settlement of disputes was first
enacted in the year 1899, known as Indian Arbitration Act. Application of this
law, however, was confined to presidency towns of Madras, Bombay and Calcutta.
Within less than two decades the law on arbitration was further codified and
brought within the ambit of Code of Civil Procedure, 1908 by way of Section 89
and Schedule –II, thereby law on arbitration was made applicable throughout
India.
To some extent, analogy of mutual settlement of disputes can also be
traced from Order 23 of CPC, which recognizes passing of compromise decrees.
Even Order XXVII Rule 5 B of CPC also mandates the courts to assist in arriving
at a settlement in the suits involving Government and public officers.
Order
XXXII was also amended in the year 1976 by way of inserting Order XXXIIA,
concerning family disputes. Order XXXIIA Rule 3 stipulates that endavour shall
be made by the courts at first instance to assist the parties in arriving at a
settlement, in consonance with other forms of alternative formulae to resolve the conflicts.
Realizing the need for a dedicated law a special and comprehensive legislation
on the subject was enacted, namely the Arbitration Act, 1940. After adoption of
UNCITRAL Model Law on International Commercial Arbitration in the year 1985 by
the United Nations the Government of India also revised their existing law and
enacted a more comprehensive law, being The Arbitration and Conciliation Act,
1996. The primary object of 1996 Act was to consolidate and amend the laws
relating to domestic arbitration, international commercial arbitration and
enforcement of foreign arbitral awards and matters connected therewith.
The arbitration law is one of the four recognized way of settlement of disputes,
viz Arbitration, Conciliation, settlement through Lok Adalat and Mediation.
Cumulatively, all these forums of settlement of disputes without direct
intervention of judicial courts are known as 'Alternative Disputes Resolution'
(briefly ADR) forums. In view of the statutory back-up almost all methodologies
of ADR have taken its root in the Indian populace, albeit much more have to be
done to achieve the motto of ADR.
The Preamble of the Constitution of India also resolves to secure Justice,
Liberty, Equality and Fraternity. With this ideology the Constitution was
amended in the year 1976 and Article 39A was inserted by way of 42nd amendment
to secure equal justice to all in conformity to Article 14. To promote equal and
easy access to justice both the central as well as state legislature has enacted
laws and have adopted various polices for the advancement of these
constitutional aspirations.
The prominent law in this regard is Legal Services
Authority Act, 1987. Very recently the Government of India has also enacted a
special legislation to stream line the procedure for resolving disputes by way
of mediation, namely -The Mediation Act, 2023. This reflects the commitment of
the Government to encourage resolution of disputes through various forums of ADR.
It is said that a law is effective if the statute conforms to the rule of law;
the degree of acceptance by the people ; the degree to which people feel
protected under the laws and its processes; the way people feel the law is in
their interest and not against them and if the law is cost and time effective.
People's confidence also depends on the flawless enactment of the law. People
lose their confidence in the law more if there are frequent amendments.
Precisely, this is the story of 1996 Act.
In this small piece of article, I will confine myself only to certain provisions
of The Arbitration and Conciliation Act, 1996 pertaining to domestic
arbitrations. The original Act has undergone major reforms three times within a
short period of less than two decades. This is not a good sign to keep the
confidence of its stakeholders, though the amendments must have been made to
make the law more effective.
Drafting of legislations is not only an art, but it is also a science. The
persons, who are responsible for drafting legislations, should not only possess
the skills of drafting but they should also have mastery over the subject. In
appropriate cases opinions and views of experts in the field should also be
taken and considered.
A perfect and well crafted legislation is likely to bring
results and achieve the objectives for which it is enacted whereas a defective
legislation not only shatters the hope of legislators but also leads to chaos,
miscarriage of justice and injustice to the victims of such law. The Arbitration
and Conciliation Act, 1996 is one such defective law.
The Arbitration and Conciliation Act was enacted in the year 1996 with the
primary objective to render easy, affordable and speedy justice in the realm of
commercial disputes. This adjudicatory system is parallel to scores of tribunals
and similar other authorities. Whether these alternative adjudicatory systems
are fulfilling the aspirations of the legislators and the litigants is seriously
debated.
Very recently, the Ministry of Finance Department of Expenditure, Govt.
of India has issued certain guidelines vide Office Memorandum dated 03.06.2024,
whereby the Govt. departments/PSUs and its agencies have been advised to refrain
from incorporating the arbitration clause in the tenders/contract agreements in
a routine manner. These guidelines have made a somersault of the avowed
objectives of ADR and it should be an eye opener for the Government about
serious malaise existing in the arbitration law.
Commencement of the proceeding:
Section 21 of the Act reads as follows:
21. Commencement of arbitral proceedings:
Unless otherwise agreed by the parties, the arbitral proceedings in respect of a
particular dispute commence on the date on which a request for that dispute to
be referred to arbitration is received by the respondent.
Section 21 has to be read and understood in juxtaposition to Sec. 23 (4) and
Sec. 29A of the Act. Relevant provisions are also reproduced below for ready
reference:
23. Statements of claim and defence:
- xxx
- The statement of claim and defence under this section shall be completed
within a period of six months from the date the arbitrator or all the
arbitrators, as the case may be, received notice, in writing of their
appointment.
29A. Time limit for arbitral award:
- The award in matters other than international commercial arbitration
shall be made by the arbitral tribunal within a period of twelve months
from the date of completion of pleadings under sub-section (4) of
section 23:
Provided that the award in the matter of international commercial
arbitration may be made as expeditiously as possible and endeavor may be
made to dispose of the matter within a period of twelve months from the
date of completion of pleadings under sub-section (4) of section 23.
The purpose of fixing 12 months period for passing an award from the date of
completion of pleadings as provided under Sec. 23 (4) can be understood.
However, the date of commencement of arbitral proceeding and the date of
completion of pleading, as contemplated in Sec. 21 and Sec. 23 (4) of the Act
are misleading. The date of passing of award U/s Sec. 23 (4) has relevance for
the purpose of filing an application U/s 34 for setting-aside the award.
However, the significance of the commencement of the proceedings, as provided in
S.21, is misleading and confusing.
Sec. 21 speaks about notice by one party to
the other but the basis for this notice is missing. It should have been clearly
spelled out that this notice is for referring the dispute for arbitration.
Strangely, Sec. 11 that deals with the issue of appointment of arbitrators
nowhere has a reference of S. 21. Since, S. 29 A and S. 23 (4) take care of the
period of completion of the proceedings S. 21 is practically an otiose, without
specifying the motive of request to the respondent.
Date of Reference:
Sec. 2 of the Act describes the definitions of various terms. However, the
legislators deliberately or inadvertently omitted to define the 'date of
reference'. Since, the entire law is focused on time bound resolution of the
disputes it would have been prudent to prescribe a specific date of reference to
the tribunal to compute the subsequent steps.
However, the tribunals are falling
upon Sec. 23 (4) and Sec. 29A for this purpose. Sec. 29A says that the award
should be passed within 12 months of completion of pleading, as provided in Sec.
23 (4). However, Sec. 23 (4) is essentially for completing the pleadings within
a period of 6 (six) months from the date the arbitrator (s) receive notice of
his appointment. It is not clear as to how the parties will come to know about
the date receipt of notice of appointment by the arbitrator, in case the
appointment is made by the High Court.
The period of completing the arbitral proceedings within 18 months of reference
also needs to be revisited. In the civil suits under Code of Civil Procedure,
1908 the ordinary date of commencement of the hearing is the date of framing of
issues. Similarly, in criminal cases the date of beginning of trial connotes the
date of framing of charges. Very recently, an issue has been raised before the
Hon'ble Supreme Court that the commencement of hearing of civil suits should be
regarded from the date of filing of evidence on affidavits and cross-examination
of witnesses.
Practically, on receipt of the letter of appointment the arbitrator issue
notices for appearance of parties. Sometime, notices are either not served on
time or sometime the parties do not appear for very many bonafide reasons.
Hence, the date of commencement of the hearing of arbitration proceedings from
the date of receiving notice by the arbitrator (s) is redundant. Hence, I
suggest that the first date of filing of Statement of Claims should be the ideal
date for reckoning the date of commencement of arbitral proceeding.
Imbroglio about Schedule IV:
I must acknowledge the foresightedness of the legislature in bringing a model
chart regarding fee of the arbitrators by the way of introducing 4th Schedule in
the 1996 Act. This chart has greatly removed the disparity of fee charged by the
arbitrators. Though private parties had no difficulty in negotiating the fee of
the arbitrator(s) the government departments and their agencies were facing
hindrances in finalizing the fee the arbitrator(s). The process of settling the
fee of the arbitrator(s) consumed valuable time of the arbitral proceedings.
While speaking on the usefulness of Schedule IV in the Arbitration Act I am
reminded with the chart of compensation brought out by the legislators while
enacting Motor Vehicles Act, 1988 in the Second Schedule under the nomenclature
of 'Schedule for compensation for third part fatal accident/injury cases
claims'.
Though the intention of the legislators was quite appreciable the
courts found gross infirmities in the formulae of compensation during the course
of scrutiny of the compensation table. However, with the intervention of
judiciary the defects in the table have been largely rectified by way of
judicial pronouncements. Similar is the case with Schedule IV of the Arbitration
Act.
The Hon'ble Supreme Court made all efforts to rectify the defects in Schedule IV
in the judgment of Oil And Natural Gas Corporation Ltd. (ONGC) and Afcons
Gunanusa : 2022 SCC Online SC 1122. However, despite extensive research and
deliberations the apex court could resolve only a couple of ambiguities.
In the
said case, the apex court primarily concentrated to define what is 'sum in
dispute', arbitrators fee qua Schedule IV and arbitrators fee in case of multi
member tribunal and that counter claim shall be treated as an independent 'sum
in dispute'. However, many more questions neither raised nor decided by the Hon'ble Supreme Court with reference to Schedule IV.
To my understanding Schedule IV is still confusing. The 'sum in dispute' in
ordinary parlance reflects the amount of claims and counter claims. However,
there are many instances where the parties seek only declaratory awards without
consequential reliefs in terms of money. What would be the 'sum in dispute' in
such a scenario.
Though the 1996 Act was amended in 2015, 2019 and 2021 there was no attempt to
revise the fee schedule prescribed under the Act. The legislators were prompt
enough (quite justified) to prescribe the time limit for completing the
pleadings and also passing the award. However, they were oblivious of revising
the fee schedule beyond the statutory period of 18 months to complete the
arbitral reference, price escalation apart. To put it differently, the fee
prescribed in Schedule IV would mean the fee is for a period of 18 months. There
is no clarity in the law, precisely Schedule IV, as to whether the arbitrator(s)
shall be entitled to extra remuneration beyond the original period of 18 months.
Though the Hon'ble Supreme Court, in the case of ONGC vs. Afcon, has held that
Fourth Schedule is not mandatory and party autonomy will prevail over the
schedule practical difficulties will still arise until and unless Schedule IV is
revised in the context of high stake claims.
Despite giving autonomy to the
parties to negotiate the fee of arbitrator(s) it will still be difficult for the
officers, representing various government departments, to agree for any amount
of fee instaneously over the counter. Invariably, the officers have to forward
the proposal to the higher authorities for approval and this period will overlap
the statutory period of 18 months. Hence, it is desirable that Schedule IV
should be updated keeping open the scope of further negotiation.
Presently, 4th Schedule contemplates average 'sum in dispute' to be that of 20
crores, whereas in reality majority of the arbitration disputes overshoots the
claim amount of Rs. 20 crores. In the case of ONGC vs. Afcon itself the 'sum in
dispute' ran above 1000 crores and case also involved complexity of issues with
voluminous documents.
These were the compelling circumstances that forced few
arbitrators to withdraw from the tribunal. If the 4th Schedule is revised
pragmatically and a more sound, scientific and pragmatic formula is devised it
would be easier to settle the arbitrators' fee and this will certainly save the
time of the tribunal in deciding the dispute.
Ambiguity and Dispensable Section 34:
In this Chapter I would like to visit the most contentious provision of Sec. 34
that enables the parties to challenge an award in two parts. In the first part I
will confine to the ambiguity of the law and in the 2nd part I will briefly
discuss the necessity of this provision in the Act at all.
A. Contours of Sec. 34
Chapter VII of the Act deals with procedure as to how an award can be
challenged. It consists of only Sec. 34 with its sub-sections. The marginal
heading of Sec. 34 stipulates that an application in this regard should be filed
in the 'court', without specifying which court. For this purpose the definition
of 'court' has to be borrowed from Sec. 2 (1) (e). The grounds to challenge the
award have been elaborated in sub-section (2). Under Sec. 34 such an application
has to be filed in the civil court of original jurisdiction in case of domestic
awards and the awards arising out of international commercial disputes have to
be filed in the high court.
A cursory look to this provision makes it clear that the court of District Judge
is the competent forum to challenge domestic awards. The contours of this court
have been shackled with the limitations provided in sub-section (2). The grounds
to challenge the award under Sec. 34 (2) (a) are intrinsically technical in
nature. If an award is challenged on any of the grounds laid down there in the
court need not re-evaluate the merit of the case and award.
Only a lee way has
been given to the court to scrutinize the justiceability of the award is under
Sec. 34 (2) (b) (ii) and (iii), which provides that an award can be set-aside if
it is in conflict with the fundamental policy of Indian law or if the award is
in conflict with most basic notions of morality or justice. 'Public Policy' for
this purpose has been explained in the 'Exception' thereto that brings into
picture the scope to interfere with the award on the ground of fraud or
corruption and morality.
There are umpteen numbers of judicial authorities where it has been held that
the arbitral tribunal is the master of facts and the courts cannot interfere
with the award on merit. In the case of NHAI vs Hakeem: (2021) 9 SCC 1 the apex
court further went to opine that the new Act was brought into being with the
express parliamentary objective of curtailing judicial intervention. In the case
of M/s. Dyna Technologies Pvt Ltd. Vs Crompton Greaves Limited: (2020) 1 SCALE
121 also the Apex Court has candidly and categorically repeated that section 34
is different in its approach and cannot be equated with a normal appellate
jurisdiction.
Their Lordships further observed that if the courts were to
interfere with the arbitral awards in the usual course then the commercial
wisdom behind opting for ADR would stand frustrated. In a recent judgment in the
case of S.V. Samudram Vs. State of Karnataka: (2024) 3 SCC 623, the Hon'ble
Supreme Court has reiterated that the courts under Sec. 34 have no jurisdiction
to modify arbitral awards and any attempt to modify an award assuming its power
U/s 34 and 37 would amount to crossing "Lakshman Rekha".
However, a different line of approach was taken by the Apex Court in a series of
judgments viz., Vedanta Limited vs. Shenzden Shandong Nuclear Power Construction
Company Limited, Oriental Structural Engineers Pvt. Ltd. vs. State of Kerala and
M.P. Power Generation Co. Ltd. vs. Ansaldo Energia Spa and three Judges in J.C.
Budhraja vs. Chairman, Orissa Mining Corporation Ltd., Tata Hydroelectric Power
Supply Co. Ltd. vs. Union of India and Shakti Nath vs. Alpha Tiger Cyprus
Investment. In view of these conflicting approaches to Sections 34 and 37 the
Hon'ble Supreme Court has referred the issue of scope of courts U/ss 34 and 37
to a larger bench vide order dated 20.2.2024 in the case of Gayatri Balasamy Vs.
M/s ISG Novasoft Technologies Ltd with the following terms of reference:
- Whether the powers of the Court under section 34 and 37 of the Arbitration and Conciliation Act, 1996, will include the power to modify an arbitral award?
- If the power to modify the award is available, whether such power can be exercised only where the award is severable and a part thereof can be modified?
- Whether the power to set aside an award under section 34 of the Act, being a larger power, will include the power to modify an arbitral award and if so, to what extent?
- Whether the power to modify an award can be read into the power to set aside an award under section 34 of the Act?
- Whether the judgment of this Court in Project Director NHAI vs. M. Hakeem, followed in
Larsen Air Conditioning and Refrigeration Company vs. Union of India and SV Samudram vs. State of Karnataka lay down the correct law, as other benches …..have either modified or accepted modification of the arbitral awards under consideration?
The aforesaid divergent views clearly reflect the lacunae in the law and needs
to be clarified and resolved at the earliest possible.
B. Whether Section 34 is dispensable?
The motto to create Tribunals and various other ADR authorities is to provide
affordable, easy and speedy justice to all. With the same dictum arbitral laws
were also introduced globally and given gradual priority in resolving all kinds
of disputes. Whether this parliamentary intent has been fulfilled/achieved in
the last more than one century of codified laws on arbitration, more
particularly the 1996 Act in India.
I have already discussed few aspects relating to the cost of litigation even if
the disputes are settled through informal forums. However, the main hurdle to
get speedy justice is the availability of multiple forums to challenge arbitral
awards despite the fact that such tribunals are reposed with faith by the
contending parties in the realm of "party autonomy".
Though Sec. 34 has provided very limited scope of interference in the arbitral
awards instances are galore that both district and high courts overstep their
jurisdiction and interfere with awards at random. Precisely, this was the reason
to refer the matter to a larger bench by the Apex Court to examine the contours
of Sections 34 and 37 of the Act.
Except four High Courts, no other high court has the original jurisdiction. As a
corollary, all applications U/s 34 have to be necessarily filed and adjudicated
by the Courts in the rank of District Judges irrespective of value of the Award.
No limitation has been prescribed either in the Act or in the High Court Rules
to set any bar for the civil courts as regards their pecuniary limit in the
context of Sec. 34 applications.
There are instances where awards have been passed by multi member tribunal,
consisting of retired supreme court and high court judges and the 'sum in
dispute' may run in thousand crores even then the applications U/s 34 have to be
necessarily filed before innocent district judges. In such a riddle and
conundrum, the district judges are sandwiched to scrutinize the legality of the
award.
As stated above, tribunals have been created to give speedy and quick justice,
without rigour of normal judicial courts and also to give succor to the
judiciary who are overburdened with millions of cases and their docks are
overcrowded. If the arbitral awards are also to be scrutinized by the same set
of judicial courts where is the justification to create arbitration laws.
Making statutory provision of application before the court U/s 34 ipso facto is
against the concept and principle of "party autonomy". Even if there is no
stipulation in the contractual documents of appeal against the award the losing
parties usually invoke Sec. 34 since the legislation has given this scope.
Besides this, appeals in the high court are also laid on the same set of grounds
provided U/s 34 and the awards are scrutinized within the same parameters and
arguments. Hence, there does not appear to be any justification for retaining
Sec. 34 in the Act.
Though the arbitration act has set time limit for filing pleadings and rendering
awards there is no such time limit for the courts. Since the district courts and
high courts are already overburdened the disputes linger for decades and the
award holders are deprived of getting the fruits of decrees in their favour
besides burdening them with additional litigation costs. There are instances
where district courts have not been able to decide applications U/s 34 even
within a decade's period.
This fact alone is sufficient to remove this provision from the law. Whatever
grounds have been provided to the civil courts U/s 34 are available with the
high courts U/s 37 and there is no need of duplication of layer of litigation.
Further appeal to the Hon'ble Supreme Court under Article 136 is another forum
in the existing hierarchy of courts.
Under normal Code of Civil Procedure a final decree is challenged by way of an
appeal. However, in the case of arbitral awards a miscellaneous case is
registered in the civil courts, who are already confused about their authority,
power and jurisdiction to interfere with the awards.
Since the appellate power has already been vested with the high courts where is
the need of an intermediary judicial authority to examine the correctness and
legality of the arbitral awards. This is just a superfluous authority under the
garb of Sec. 34 and it should be done away with in the interest of the litigants
and society at large. Withdrawing Sec. 34 from the Act will also fulfill the
aspirations of the parliament to get speedy and affordable justice to the
people.
There are many more infirmities, flaws, loopholes and shortcomings in the
arbitration law. However, for brevity of this short legal discourse I give a
pause to this article with the deliberation on a few issues only.
[
NOTE: The words “Court of District Judge” would include “Commercial Courts”]
Written By: Justice B D Agarwal, Former Judge, Gauhati High Court
Date: 25.06.2024
Please Drop Your Comments