Judicial Bulging of Grounds
Bank Guarantee is the common mode, of securing payment of money in commercial
dealings as the beneficiary, under the Guarantee, is entitled to realise the
whole of the amount under that Guarantee in terms thereof irrespective of any
pending dispute between the person on whose behalf the Guarantee was given and
the beneficiary as laid down in the case of
Hindustan Construction Co. Ltd.
v. State of Bihar & Ors., AIR 1999 SC 3710.
In
Himadri Chemicals Industries Limited v. Coal Tar Refining Co., (2007)
8 SCC 110 apex court laid down the principles for grant or refusal to grant of
injunction to restrain enforcement of a bank guarantee;
While dealing with an application for injunction where unconditional bank
guarantee is given or accepted, the beneficiary is entitled to realize such a
bank guarantee irrespective of any pending disputes relating to the terms of the
contract.
The bank giving such guarantee is bound to honour it as per its terms
irrespective of any dispute raised by its customer.
The courts should be slow in granting an order of injunction to restrain the
realization of a bank guarantee.
Since a bank guarantee is an independent and a separate contract and is absolute
in nature, the existence of any dispute between the parties to the contract is
not a ground for issuing an order of injunction to restrain enforcement of bank
guarantees.
Fraud of an egregious nature which would vitiate the very foundation of such a
bank guarantee and the beneficiary seeks to take advantage of the situation.
Allowing encashment of an unconditional bank guarantee would result in
irretrievable harm or injustice to one of the parties concerned.
Performance Bank Guarantee (PBG) being an independent contract, yet subject to
various exceptions developed by judicial adjudication and interpretation in
various cases, has swollen its own compartment.
Where an injunction against encashment could only be granted in a case where:
Invocation is not in terms of the bank guarantee, or a case of established
egregious fraud is made out which is known to the bank and is practiced by the
beneficiary of the bank guarantee, or where a case of special equities is made
out so as to prevent irretrievable injustice between the parties, or
Irretrievable Injury, or under Economic duress; is now available to the
plaintiff on grounds which are too remote from causing grave injustice or
prejudice to the defendant. Thence, diluting the autonomous character of the
contract of PBG and blurring the right of the beneficiary.
Fraud has further been broadened to include œall acts, omissions and
concealments which involve a breach of legal or equitable duty, trust or
confidence, justly reposed and are injurious to another or by which undue and
unconscientiously advantage is taken of another. Fraud must be specifically
pleaded so as to be taken up as a ground mere representation of circumstances
may not lead to inference/instance of fraud, same was held in the case of
Omaxe Const. Ltd. v. UOI, (2004) 2 ArbLR 1985 Cal 23.
Where sufficient area for work to proceed was not provided the court found it
correct to grant injunction over encashment of guarantee. In a similar case of
A.M.F. (International) Ltd. V. Marshall, (1986) 208 EG (3d) 542 Court
propounded if the site for construction isn't ready to be handed over or lacks
what had been promised Bank Guarantee cannot be encashed. Further, in a case, if
contractor/ builder puts any change with respect to time length/ line or
performance and the same is authorized or agreed upon by parties, contractor
cannot substitute and get the same done by some other party as laid down in
Tencred Arrol &Co. v. Steel Co. of Scotland, (1974) 48 ALJR 461.
Doctrine of substantial performance is yet another ground which is considered by
Courts outside India but has not been argued in India much. In
Dakin v. Lee,
(1916) 1 KB 566 substantial performance was held to be a ground to refute the
claim of encashment of bank guarantee. Sufficient performance of a contract is
referred to as substantial performance.
In case of delay caused by the owner i.e. party claiming encashment of BG no
liquidated damages can be granted is a settled rule since the case of
Holme
v. Guppy, (1838) 3 M&W 387 had been decided. In circumstances where
substantial work is done and encashment of BG is claimed an amount only to the
extent of non-paid bills can be encashed, same has been observed by Hon'ble High
Court of Delhi in
Nangia Construction (India) Ltd. V. International Airport
Authority of India, AIR 1992 Del 242. In a similar case of
National
Project Const. Corporation v. G. Ranjan, AIR 1985 Cal 23, Court held in a
case where mobilization advance was given, only the balance amount which is not
recovered can be encashed via Bank Guarantee.
Further, Courts have also included the elements of misrepresentation and
suppression to be valid grounds for grant of injunction against encashment of
bank guarantee.[5]
Conclusion
The above catena showcases- how a compartment develops and spacifies its
components. From a few available grounds for seekinginjunction over encashment
of Bank Guaratees, Couts have looked into the genuineness of applications;
seeking such injunction, and have laid down various grounds for the same.
End-Notes:
- Parampujya Solar Energy Private Limited v. Union of India and Ors.,
MANU/DE/1026/2018DSC Limited v. Rail Vikas Nigam Limited & amp Ors.,MANU/DE/2437/2013,Larsen
& Toubro Limited v. Maharashtra State Electricity Board and Others, (1995) 6
SCC 68 etc
- Dai-ichi Karkaria Private Ltd., Bombay vs. Oil & Natural Gas Commission
Bombay and another,MANU/MH/0053/1992
- ibid
- R. v. Walter Cabott Construction Ltd., (1975) 69 DLR (3d) 542
- Synthetic Foams Ltd. v. Simplex Conc. Piles (India) Pvt. Ltd, AIR 1988
Del 207
Banking Laws Articles
Please Drop Your Comments